Capacity Market supplier charge

Latest published rate, who sets it, and where it is forecast to go.

What Capacity Market supplier charge is, who sets the rate, what the revenue funds and where it is heading. Rates come from the Purely Energy non-commodity cost data hub; forecasts are our own.

Roughly 2 to 3% of a typical UK business electricity bill

Latest published rate
0.4500p/kWh
2024/25+18.4% vs 2023/24
Forecast
0.5000p/kWh
2025+11.1%
Share of bill
2 to 3%
Of a typical UK business bill
Set by
EMR Settlement Limited (based on DESNZ/NESO auction clearing prices)
All electricity supplies (weighted to winter peak demand)

Capacity Market supplier charge: what it is, who charges it, and what it pays for

What it is

The Capacity Market supplier charge charge in plain English

Pays power stations and demand-side response to be available during winter peaks. Ensures the lights stay on during cold snaps. Based on T-4/T-1 auction clearing prices.

Introduced 2014 (Energy Act 2013). T-4 auctions run 4 years ahead.

Who charges it

The body that sets the rate

EMR Settlement Limited (based on DESNZ/NESO auction clearing prices)

Unit

p/kWh

Applies to

All electricity supplies (weighted to winter peak demand)

What it pays for

Where the revenue ends up

Security of supply, keeping generators available for peak demand

Share of typical bill

2 to 3%

EMR Settlement's Capacity Market supplier-charge rates put the levy at roughly 2 to 3% of a typical non-domestic electricity bill.

Published rate history

Financial yearRateYear on yearSource
2020/210.1960p/kWh-Published
2021/220.2220p/kWh+13.3%Published
2022/230.2950p/kWh+32.9%Published
2023/240.3800p/kWh+28.8%Published
2024/250.4500p/kWh+18.4%Published

Forecast trajectory

Forecasts from our non-commodity cost model. P10, P50 and P90 are the 10th, 50th and 90th percentile outcomes; P50 is the central estimate.

YearP10P50P90ConfidenceRationale
2025-0.5000--
2026-0.5400--
2026-270.59400.64000.6800highBased on published T-4 auction results and EMR Settlement methodology
2027-0.5700--
2027-280.68000.73000.7800highDirect calculation from known auction results using established cost recovery methods
2028-0.5900--
2028-290.75000.81000.8700highReflects £63/kW/year T-4 auction result with standard allocation methodology
2029-0.6100--
2029-300.80000.88000.9600medAssumes continued thermal retirements and demand growth patterns
2030-0.6300--
2030-310.85000.95001.050medElectrification demand growth with uncertain capacity replacement timing
2031-0.6426--
2031-320.75000.94001.130lowRegulatory uncertainty and potential market design changes post-2030
2032-0.6555--
2032-330.70000.92001.140lowSpeculative given no auction data and policy uncertainty
2033-0.6686--
2033-340.68000.91001.140lowPlaceholder estimate with wide uncertainty bands
2034-0.6819--
2034-350.69000.92001.150lowHighly uncertain given potential fundamental market structure changes

Capacity Market supplier charge FAQs

What is the Capacity Market supplier charge charge?

Pays power stations and demand-side response to be available during winter peaks. Ensures the lights stay on during cold snaps. Based on T-4/T-1 auction clearing prices.

Who sets the Capacity Market supplier charge rate?

The Capacity Market supplier charge rate is set by EMR Settlement Limited (based on DESNZ/NESO auction clearing prices).

What does Capacity Market supplier charge pay for?

Capacity Market supplier charge revenue supports Security of supply, keeping generators available for peak demand.

What is the latest published Capacity Market supplier charge rate?

For 2024/25, the published Capacity Market supplier charge rate is 0.4500 p/kWh.

What is the Capacity Market supplier charge forecast?

Our latest forecast for 2025 is 0.5000 p/kWh.

Related charges in Renewables and capacity

Rate data from the Purely Energy non-commodity cost data hub (dh.purelyenergy.co.uk). Published rates come from statutory publications by the body listed above; forecasts are modelled from published guidance and market trends, so treat P50 as a central estimate and use P10/P90 for sensitivity. Primary source