Skip to main content

UK non-commodity charge · Transmission · Electricity

TNUoS fixed charges (TDR bands)

Latest published rate, who sets it, and where it is forecast to go.

What TNUoS fixed charges (TDR bands) is, who sets the rate, what the revenue funds and where it is heading. Rates come from the Purely Energy non-commodity cost data hub; forecasts are our own.

Roughly 4 to 7% of a typical UK business electricity bill

Latest published rate
0.2393to5698.39GBP/MPAN/day
2026/27
Forecast
-
Share of bill
4 to 7%
Of a typical UK business bill
Set by
NESO (National Energy System Operator), final tariffs published each January for the charging year from 1 April
All electricity supplies, banded by voltage and agreed capacity

TNUoS fixed charges (TDR bands): what it is, who charges it, and what it pays for

What it is

The TNUoS fixed charges (TDR bands) charge in plain English

Since April 2023 the transmission demand residual is recovered through fixed daily charges banded by connection voltage and agreed capacity (or by annual consumption for LV sites without an agreed capacity), set nationally by NESO under Ofgem's Targeted Charging Review. Your band is fixed for the charging year and appears on the bill as a pounds-per-day TNUoS or TDR line, regardless of how much you use or when.

Introduced April 2023 (Ofgem Targeted Charging Review, replacing the Triad-based residual).

Who charges it

The body that sets the rate

NESO (National Energy System Operator), final tariffs published each January for the charging year from 1 April

Unit

GBP/MPAN/day

Applies to

All electricity supplies, banded by voltage and agreed capacity

What it pays for

Where the revenue ends up

The national high-voltage transmission network (275kV and 400kV)

Share of typical bill

4 to 7%

NESO TNUoS tariff publications place transmission (locational plus TDR residual) at roughly 4 to 7% of a half-hourly non-domestic bill, with significant zonal variation.

Published rates by band

National rates set by NESO. Your band depends on your connection voltage and agreed capacity (or annual consumption for LV sites without one).

BandLatest publishedForecast
LV, no agreed capacity (banded by annual consumption)
LV No MIC, Band 10.2393GBP/MPAN/day2026/270.3148 (2027)
LV No MIC, Band 20.5873GBP/MPAN/day2026/270.8917 (2027)
LV No MIC, Band 31.242GBP/MPAN/day2026/271.936 (2027)
LV No MIC, Band 43.461GBP/MPAN/day2026/275.339 (2027)
LV, agreed capacity (banded by kVA)
LV, Band 15.797GBP/MPAN/day2026/278.614 (2027)
LV, Band 211.512GBP/MPAN/day2026/2717.061 (2027)
LV, Band 314.381GBP/MPAN/day2026/2721.330 (2027)
LV, Band 438.180GBP/MPAN/day2026/2757.111 (2027)
HV (banded by kVA)
HV, Band 131.839GBP/MPAN/day2026/2746.715 (2027)
HV, Band 2117.15GBP/MPAN/day2026/27174.42 (2027)
HV, Band 3185.42GBP/MPAN/day2026/27276.71 (2027)
HV, Band 4528.91GBP/MPAN/day2026/27792.81 (2027)
EHV (banded by kVA)
EHV, Band 1325.48GBP/MPAN/day2026/27461.18 (2027)
EHV, Band 21159.38GBP/MPAN/day2026/271651.14 (2027)
EHV, Band 32512.93GBP/MPAN/day2026/273448.40 (2027)
EHV, Band 45698.39GBP/MPAN/day2026/277853.84 (2027)
Unmetered (street lighting and similar)
Unmetered supplies2.568GBP/MPAN/day2026/273.512 (2027)

TNUoS fixed charges (TDR bands) FAQs

What is the TNUoS fixed charges (TDR bands) charge?

Since April 2023 the transmission demand residual is recovered through fixed daily charges banded by connection voltage and agreed capacity (or by annual consumption for LV sites without an agreed capacity), set nationally by NESO under Ofgem's Targeted Charging Review. Your band is fixed for the charging year and appears on the bill as a pounds-per-day TNUoS or TDR line, regardless of how much you use or when.

Who sets the TNUoS fixed charges (TDR bands) rate?

The TNUoS fixed charges (TDR bands) rate is set by NESO (National Energy System Operator), final tariffs published each January for the charging year from 1 April.

What does TNUoS fixed charges (TDR bands) pay for?

TNUoS fixed charges (TDR bands) revenue supports The national high-voltage transmission network (275kV and 400kV).

What are the published TNUoS fixed charges (TDR bands) rates?

For 2026/27, the published bands run from 0.2393 to 5698.39 GBP/MPAN/day depending on your voltage and capacity band.

Related charges in Transmission

Rate data from the Purely Energy non-commodity cost data hub (dh.purelyenergy.co.uk). Published rates come from statutory publications by the body listed above; forecasts are modelled from published guidance and market trends, so treat P50 as a central estimate and use P10/P90 for sensitivity. Primary source