Utility connection application

A utility connection application goes to the network operator that owns the cables, pipes or mains at your postcode: this tool names the operator, the form and the statutory timescale for electricity, gas and water, for your job type.

Routes verified against each operator's published process, August 2026

By utility:Electricity connection applicationGas connection applicationWater connection application

Free interactive application finder

Six short steps. Your answers stay in this browser tab; nothing is sent until you ask us to prepare the application.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6

Step 1 of 6: Utility

Which utility is the application for?

Pick one and we take you to that utility's page, where the operators, the forms and the timescales are its own. A site that needs more than one runs the tool once per utility.

Which operator, which form, and what the law says about the wait

There is no single national connection form for any utility. The company that owns the network at your postcode publishes its own application routes: one of six electricity distribution network operators across fourteen licence areas, one of four gas distribution networks across thirteen local distribution zones, or the water wholesaler appointed for the area. Most of them split small and large jobs at a threshold of their own. The tool above works out the operator from the postcode, or exactly from the meter identifier where the site already has one, and names the route for the job.

The first question is always who the application goes to. A new connection, more or less capacity, a move of the supply position, a diversion of the network's own assets or a permanent disconnection is the network operator's job. Removing a meter, moving it without touching the incoming cable or pipe, and switching a supply off and on for works belong to your supplier, because the supplier owns the meter. On water the same split runs between the wholesaler and the retailer. Sending a meter request to the network, or a capacity application to the supplier, costs weeks, so the tool checks the party before it names the form.

The second question is the wait. An electricity connection application runs on the quotation periods in the Electricity (Standards of Performance) Regulations 2015, in working days from a complete application; a gas connection application on the Gas (Standards of Performance) Regulations 2005. Water has no equivalent statutory quotation period: a water connection application runs on the wholesaler's own published levels of service. Each utility page carries its own routing table, statutory rows and questions.

If you only need the identity of the operator rather than the application, the network operator lookup answers that in one search, and the new energy connections guide sets out the whole process from capacity scoping to energisation, with the costs in our guide to new connection costs. When the connection is live, the supply contract on the new meter is a separate decision: request a business energy quote and we tender it across 30+ suppliers so the site never sits on a deemed rate.

Statutory quotation timescales

Working days from a complete application, set by regulation rather than by the operator. Electricity and gas have them; water does not.

Electricity: SI 2015/698

ScenarioQuotation withinInstrument
Quotation: single LV single-phase service demand connection, or a service alteration (reg 5(2))5 working daysSI 2015/698
Quotation: small project demand connection (2 to 4 LV single-phase services; 1 to 4 premises with an LV extension; a single premises with a 2 or 3 phase whole-current supply) (reg 5(3))15 working daysSI 2015/698
Quotation: any other LV demand connection (the usual class for a small commercial new connection or load increase) (reg 6(2))25 working daysSI 2015/698
Quotation: HV demand connection (reg 6(3))35 working daysSI 2015/698
Quotation: EHV demand connection (reg 6(4))65 working daysSI 2015/698
Budget estimate, capacity under 1MVA (reg 4):
10 working days
Budget estimate, capacity 1MVA or more (reg 4):
20 working days
Contact to schedule works after acceptance and payment:
7 working days (LV), 10 working days (HV), 15 working days (EHV)

Gas: SI 2005/1135

ScenarioQuotation withinInstrument
Standard quotation: new connection or alteration up to and including 275 kWh/h, or a disconnection up to 2 bar, with no site visit (GS4)4 working daysSI 2005/1135
Non-standard quotation up to 275 kWh/h (GS5)11 working daysSI 2005/1135
Non-standard quotation over 275 kWh/h (also mains diversions and disconnections at 2 bar and above) (GS6)21 working daysSI 2005/1135
Response to a land enquiry (GS8):
5 working days
Commencement and substantial completion dates, connections up to 275 kWh/h (GS9):
within 17 working days of accepting the quotation
Commencement and completion dates, connections over 275 kWh/h (GS10):
within 20 working days of accepting the quotation

Water

There is no statutory quotation period for water connections in the instruments we cite. The wholesaler's own developer-services levels of service apply. Published levels were read for 14 of the 18 wholesalers listed in the routing table below and appear under each; where none were read, the result card says so and we confirm them with the wholesaler.

Working days from a complete application. Which standard applies to a job is the operator's determination; the result card highlights the row its reading of your answer points to.

Application routes by network operator

Every electricity licence area, gas distribution zone and water wholesaler, grouped by operator, with the routes, contacts and timescales each operator publishes. 61 operators in the registry. Routes verified against each operator's published process, August 2026.

Registry verified 2026-08-30. Links appear only where the page was fetched and read; everything else is named but marked unverified until a person opens it.

Electricity: the 14 distribution licence areas

The two-digit code is the distributor id at the start of a 13-digit MPAN core. An id of 24 or above is an independent distribution network operator, listed in the next section.

UK Power Networks

  • 10 Eastern England (Eastern Power Networks plc)
  • 12 London (London Power Networks plc)
  • 19 South East England (South Eastern Power Networks plc)

Connections page: UK Power Networks (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionApplication for a new electricity connection or modification of an existing connection for works over 70kVA (UKPN16374, May 2026 v4)PDF form, fillable (from 70 kVA)dno
New connectionUnder 70kVA application (Connection Services) (opens operator site, unverified)Online portal (to 70 kVA)dno
Capacity upgrade, Capacity reductionApplication for a new electricity connection or modification of an existing connection for works over 70kVA (UKPN16374, May 2026 v4)PDF form, fillable (from 70 kVA)dno
Capacity upgradeApplication to upgrade an electricity supply (Connection Services, under 70kVA)PDF form (to 70 kVA)dno
Permanent disconnectionApplication for a new electricity connection or modification of an existing connection for works over 70kVA (UKPN16374, May 2026 v4), 'Additional works' sectionPDF form, fillabledno
Permanent disconnectionDisconnect a large supply over 400 amps (commercial) (opens operator site, unverified)Portal or formdno
Move the supply position, Divert network assets on the landApplication for a new electricity connection or modification of an existing connection for works over 70kVA (UKPN16374, May 2026 v4), Diversion work optionPDF form, fillable (from 70 kVA)dno
Temporary builder's supplyApplication for a new electricity connection or modification of an existing connection for works over 70kVA (UKPN16374, May 2026 v4), Temporary connection optionPDF form, fillable (from 70 kVA)dno
Temporary builder's supplyUnder 70kVA temporary supply application (opens operator site, unverified)Online portal (to 70 kVA)dno
MPAN generation after connection information is verified:
typically up to 10 working days (published)
  • Every www.ukpowernetworks.co.uk URL is unverified as to content; only the media.umbraco.io PDFs were read.
  • Under 70kVA versus over 70kVA is the primary routing decision: different teams, phone numbers, emails and mechanisms. Ask for expected capacity before routing.
  • Meter removal is the supplier's job. UKPN's Disconnections team removes the service and closes the MPAN only after the supplier has removed the meter.
  • The January 2023 over-70kVA form (UKPN14421) is still live at a 200 URL but superseded by the May 2026 v4; the 'uk-power-networks' Umbraco bucket is dead. Re-verify any UKPN PDF URL against the ukpn-cms bucket.
  • Guaranteed standards and quotation timescales were not captured from any UKPN document; the statutory periods in STATUTORY_STANDARDS apply.
  • Under-70kVA service alteration and disconnection pages are behind the 403 host and remain unverified.
  • The Connections Useful Contacts May 2026 PDF names staff with personal mobiles; it is deliberately not linked.

Last verified 2026-08-30.

National Grid Electricity Distribution

  • 11 East Midlands (National Grid Electricity Distribution (East Midlands) plc)
  • 14 West Midlands (National Grid Electricity Distribution (West Midlands) plc)
  • 21 South Wales (National Grid Electricity Distribution (South Wales) plc)
  • 22 South West England (National Grid Electricity Distribution (South West) plc)

Connections page: National Grid Electricity Distribution

Job typesRouteHowGoes to
New connectionSmaller connections, up to 4 properties (online application tool)Online portal (to 69 kVA)dno
New connection, Capacity upgrade, Temporary builder's supplyConnections Online Application FormOnline portaldno
New connection, Capacity upgradeNGED Application for a new or augmented connection (07-24)PDF form, fillabledno
Capacity reductionCapacity Reduction formOnline portaldno
Permanent disconnectionPermanently disconnect a supplyPortal or formdno
Move the supply positionService alteration application (online)Online portaldno
Move the supply positionNGED Application to move your electricity supply (April 2025)PDF form, fillabledno
Divert network assets on the landMove our equipment (diversions)Portal or formdno
Contact after any quotation request:
within 2 working days (published)
Connection offer validity, small commercial up to 69kVA and 5 or more properties:
offer valid 90 days; works normally completed within 90 days of acceptance (published)
Diversion offer validity:
90 days, then reapply (published)
Permanent disconnection, low voltage:
usually within 21 working days (published)
Permanent disconnection, removal of HV substation plant:
6 months notice may be required (published)
Capacity reduction takes effect:
first of the month after agreement; one change per 12 months; never backdated (published)
Response to the general enquiries form (disconnections):
within 2 working days (published)
Assessment and Design fee payment:
within 28 days of quotation; free cancellation within 10 working days of notification (published)
  • General enquiries: 0800 096 3080, Mon to Fri 8am to 5pm
  • New Supplies and applications team: nged.newsupplies@nationalgrid.co.uk
  • Capacity reduction (MIC) queries: nged.connectionspolicy@nationalgrid.co.uk
  • Meter work is out of scope for NGED: the meter itself, a short meter move with no cable change, and temporary de-energisation or re-energisation are all the supplier's job (verbatim on NGED's pages).
  • The smaller-connections tool serves a single commercial property up to 69kVA and 100A per phase; larger commercial work uses the general online form. The search-indexed 'greater-than-69kva' page returns 404.
  • Legacy westernpower.co.uk and www.nationalgrid.co.uk/connections-landing/* links return 200 with a zero-byte body: never treat them as live. NGED's own pages still carry them.
  • The footer terms link lands on a cookie page; the real terms are the General Terms and Conditions PDFs on the types-of-connection-offer page (CO general T&Cs v11 June 2026, SSQ conditions v4 June 2026, diversion works v3 Sep 2022).
  • The guaranteed standards page restates the statutory regime (headed April 2024, with payment amounts two CPIH cycles stale); the periods are in STATUTORY_STANDARDS and the amounts are not reproduced.
  • An isolation switch (2-pole or 4-pole) can be requested by phone or email so the customer's electrician can de-energise the installation without supplier visits; NGED may charge.
  • The information hub document list is client-rendered, so further forms may exist that a plain fetch cannot see.

Last verified 2026-08-30.

SP Energy Networks

  • 13 Merseyside and North Wales (SP Manweb plc)
  • 18 South Scotland (SP Distribution plc)

Connections page: SP Energy Networks (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionSP Energy Networks Customer Connections Portal, new connection (opens operator site, unverified)Online portaldno
New connection, Capacity upgrade, Temporary builder's supplyConnecting you to our network, application form guidance (form B) (opens operator site, unverified)PDF formdno
New connectionApplication Forms and Guides (opens operator site, unverified)Portal or formdno
Capacity upgradeCustomer Connections Portal, existing connection work type selector (opens operator site, unverified)Online portaldno
Permanent disconnectionCustomer Connections Portal, Disconnection (code DS) (opens operator site, unverified)Online portaldno
Permanent disconnectionDisconnecting your supply from our network, application form guidance (form D) (opens operator site, unverified)PDF formdno
Move the supply positionCustomer Connections Portal, Move Meter application (opens operator site, unverified)Online portaldno
Move the supply positionMoving your existing supply (service alteration), application form guidance (form C) (opens operator site, unverified)PDF formdno
Divert network assets on the landCustomer Connections Portal, Diversion (code DV) (opens operator site, unverified)Online portaldno
  • Zero SPEN-published content was verified. Every URL is search-index derived and must be opened in a browser before it is shown as a live route.
  • No connections phone number or email is published here: the search index returned four conflicting candidates that could not be verified.
  • No capacity reduction route was found; searches surfaced only flexibility-market services, which are not a route to reduce agreed capacity.
  • SP Distribution (id 18) and SP Manweb (id 13) are separate licensees with separate charging statements and contact numbers but share one website, portal and form set.
  • The seven quotation periods the research attributed to SPEN are the statutory SI 2015/698 standards, listed once in STATUTORY_STANDARDS.
  • Meter removal is the supplier's job; the routing is inferred from a snippet and not verified on SPEN's page.

Last verified 2026-08-30.

Northern Powergrid

  • 15 North East England (Northern Powergrid (Northeast) plc)
  • 23 Yorkshire (Northern Powergrid (Yorkshire) plc)

Connections page: Northern Powergrid

Job typesRouteHowGoes to
New connectionNew Connections (Small Works) online applicationOnline portal (to 55 kVA)dno
New connectionApplication for a New Connection, Small WorksPDF form, fillable (to 55 kVA)dno
New connectionMajor Works Application Form, June 2026PDF form (from 55 kVA)dno
Temporary builder's supplyTemporary Connection Application Form, June 2026PDF formdno
Capacity upgrade, Capacity reductionAdditional Load Application Form, June 2026PDF formdno
Capacity upgrade, Capacity reductionModify a connection (Service Upgrade)LoginOnline portaldno
Permanent disconnectionDisconnection Application FormPDF form, fillabledno
Permanent disconnectionDisconnections online applicationLoginOnline portaldno
Move the supply positionMove Your Meter Position (Service Alterations)LoginOnline portaldno
Divert network assets on the landRelocate our equipment (Diversion)LoginOnline portaldno
Move the supply position, Divert network assets on the landMoving Connections guidancePortal or formdno
Authority to actAuthority to Act FormPDF form, fillabledno
Service alteration, average time to quotation:
4 days (published)
Service alteration, average time to connect after payment:
6 weeks (published)
One standard connection, average time to connect after payment:
6 weeks (published)
Typical small business connection, average time to quotation:
27 days (published)
Typical small business connection, average time to connect after payment:
24 weeks (published)
Typical large business connection, average time to quotation:
40 days (published)
Typical large business connection, average time to connect after payment:
50 weeks (published)
EHV connection, average time to quotation and to connect:
68 days; 2 years (published)
Disconnection, average time to receive a quotation (small or large business):
25 days (published)
Connection Offer Expenses cooling-off period:
5 working days from confirmation that all information is held (published)
Single Point of Contact allocated after application:
within 5 days (published)
Requote eligibility after an offer expires:
6 months (published)
  • Connections helpline: 0800 011 3433, Mon to Fri 8am to 8pm, Sat 9am to 5pm
  • Minicom / textphone: 0800 028 9507, 24 hours
  • General connections: getconnected@northernpowergrid.com
  • Routing threshold is 80A per phase (about 55kVA three-phase): at or below use the fillable Small Works PDF or public portal, above use the flat Major Works June 2026 form.
  • All three June 2026 forms (Major Works, Additional Load, Temporary Connection) are flat PDFs with zero fields; the older 2022 and 2023 forms are fillable.
  • Only the Small-Works portal is public; Service-Upgrade, Service-Alterations, Diversion and Disconnections all require an SSO account.
  • No meter removal form exists: the meter is the supplier's asset. The Disconnection route removes Northern Powergrid's own equipment.
  • Guide prices are indicative, undated and separate from Connection Offer Expenses; do not present a guide price as a quote.
  • Northeast (id 15) and Yorkshire (id 23) have separate charging statements, both dated September 2025.
  • The 'New Point of Connection' row on the forms index carries no link; the working PoC route is the SSO login.
  • Postal address on the forms index: FREEPOST RTSJ-LHKB-LTST, Northern Powergrid Connections, Alix House, Falcon Court, Preston Farm Industrial Estate, Stockton on Tees, TS18 3TU.

Last verified 2026-08-30.

Electricity North West

  • 16 North West England (Electricity North West Limited)

Connections page: Electricity North West

Job typesRouteHowGoes to
New connection, Capacity upgrade, Move the supply position, Permanent disconnection, Divert network assets on the land, Temporary builder's supplyApplication for electricity connection (1-4 connections up to 60kVA), v2PDF form, fillable (to 60 kVA)dno
New connection, Capacity upgrade, Move the supply position, Divert network assets on the land, Temporary builder's supplyApplication for electricity connection (1-4 connections up to 60kVA), web formOnline portal (to 60 kVA)dno
New connection, Capacity upgrade, Temporary builder's supplyFive or more connections or a single connection over 60kVA (up to 300kVA), web formOnline portal (from 60 to 300 kVA)dno
New connection, Capacity upgrade, Move the supply position, Permanent disconnection, Divert network assets on the land, Temporary builder's supplyApplication for electricity connection (5 or more connections or single connection over 60kVA)PDF form, fillable (from 60 kVA)dno
New connection, Capacity upgrade, Move the supply position, Divert network assets on the land, Temporary builder's supplyApplication for single connection over 300kVA, web formOnline portal (from 300 kVA)dno
Capacity upgradeUpgrade or reduce your supplyPortal or formdno
Capacity reductionMIC reduction request (email)Emaildno
Permanent disconnectionDisconnect your supplyPortal or formdno
Move the supply positionMoving your meter (service alteration)Portal or formdno
Divert network assets on the landDiversion of ENWL mains or assetsEmaildno
New connection, Move the supply position, Permanent disconnectionOnline estimate portalOnline portal (to 20 kVA)dno
1-4 properties online application, quote:
within 5 working days (published)
1-4 properties, connection after site ready and payment:
on average four to six weeks (published)
New connection generally (FAQ):
six to eight weeks from site ready, on average (published)
Meter move / service alteration:
4 to 6 weeks from payment (published)
Disconnection scheduling:
six to ten weeks notice on the web page (the booklet says six to eight weeks from payment); supplier notice minimum 10 days single meter, 25 days multiple (published)
Diversion design solution:
20 to 35 working days after application; estimate valid 180 days (published)
Connection Offer Expenses invoice:
30 days to pay or the offer becomes invalid (published)
  • Connections Application Support: 0800 988 1730, Mon to Fri 8am to 5pm
  • Pre-Application Support: 0800 988 1732
  • Applications, 1-4 properties and connections up to 5MVA: connectionapplications@enwl.co.uk
  • Pre-application support: preapplicationsupport@enwl.co.uk
  • Disconnections: disconnections@enwl.co.uk
  • Diversions: diversions@enwl.co.uk
  • Connections over 5MVA: gandpconnections@enwl.co.uk
  • MIC reductions: Termsandconditions@enwl.co.uk
  • Commercial capacity (MIC) queries: flexible.contracts@enwl.co.uk
  • Thresholds: 1-4 form up to 60kVA; 5+ web form 60 to 300kVA; over-300kVA form above that; over 5MVA by email; CT metering from 61kVA (EPD-283 LV Design Manual).
  • Two live 1-4 PDFs exist with different field names: the v2 dated 4 June 2026 is current; the non-v2 (21 May 2026) is what the meter-move and disconnection pages link.
  • The June 2026 forms carry the new postal address: Connections, SP Electricity North West, Frederick Road, Salford, M6 6QH. Emails and the legal entity are unchanged after the rebrand.
  • Meter removal is the supplier's job: the disconnection booklet says the meter should be removed by the supplier before ENWL disconnects the service.
  • Both application PDFs carry a 'Re-energise existing supply' checkbox; the wizard still routes re-energisation to the supplier first.
  • The 2019 PDFs (application-for-connection-5.pdf, disconnect-your-supply-application-form.pdf) still resolve but are superseded; domestic-connections-1-to-4-form.pdf is 404.
  • Guaranteed standards in the GSOP PDF (April 2026) are the statutory regime, listed once in STATUTORY_STANDARDS.
  • Regional portal phone numbers (01772 472 140, 0161 455 5540) appear on the estimate portal but were not confirmed elsewhere and are omitted.

Last verified 2026-08-30.

SSEN Distribution

  • 17 North Scotland (Scottish Hydro Electric Power Distribution plc)
  • 20 Southern England (Southern Electric Power Distribution plc)

Connections page: SSEN Distribution

Job typesRouteHowGoes to
New connection, Temporary builder's supplyConnect 1-4 properties (My Profile portal)LoginOnline portal (to 69 kVA)dno
New connection, Capacity upgrade, Temporary builder's supplyOffline Application, 1-4 small connections (new connections or load increases for up to 4 residential or small business premises)PDF form, fillable (to 69 kVA)dno
New connectionConnect 5 or more properties (residential or commercial development)LoginOnline portal (from 69 kVA)dno
New connectionOffline Application, 5 or more connectionsPDF form, fillable (from 69 kVA)dno
New connectionConnect a large project (large housing, commercial or industrial development)LoginOnline portal (from 300 kVA)dno
New connection, Capacity upgradeOffline Application Form, new connections or load increases to serve industrial and commercial developmentsPDF form, fillabledno
Capacity upgrade, Capacity reductionChange in capacity (increase or decrease in load)LoginOnline portaldno
Permanent disconnectionDisconnect my electricity cable (permanent disconnection)LoginOnline portaldno
Temporary disconnectionTemporary isolation (power off for works, up to 72 hours)LoginOnline portaldno
Move the supply positionMove my electricity meter (service alteration)LoginOnline portaldno
Move the supply positionApplication to move an existing connection (service alteration)PDF form, fillabledno
Divert network assets on the landDivert my electricity supply (network, service cable or substation diversion)LoginOnline portaldno
Divert network assets on the landOffline application, diversionsPDF form, fillabledno
1-4 property new connection, temporary builders supply, load increase, meter move or diversion: first contact from the quoter:
within 5 working days of application (published)
1-4 property new connection, load increase, meter move or diversion: quotation issued:
5 to 15 working days depending on complexity; quote valid 90 days (published)
Small works start after payment:
aim to begin within 4 weeks (6 to 8 weeks where permits or land rights are needed); project manager contact within 2 days of payment; works complete within 90 days of payment (published)
Disconnection:
quoter contact within 10 working days; works typically within 4 weeks; confirmation letter within 5 working days of completion (published)
Large connection quotation after all information is received:
LV 25, HV 35, EHV 65 working days (SSEN restating the statutory periods) (published)
  • Connections (option 2 new connections, diversions and service alterations; option 3 general enquiries): 0800 048 3516, weekday office hours
  • Connections applications: connections@ssen.co.uk
  • General enquiries and temporary isolation: ge@ssen.co.uk
  • Several offline forms exist in two variants: the Havant PO9 1QH / connections@ssen.co.uk versions are current; the Cosham PO6 1UJ versions with a legacy sse.com email are superseded even where a live page still links them.
  • The hub says 5+ and large-project routes start above 69kVA while the large-connections page says above 300kVA; unreconciled, both as published.
  • Contact hours are given as 08:00 to 16:00 on the contact page and 08:00 to 17:00 on service pages; treated as weekday office hours.
  • No offline PDF exists for a metered disconnection or a capacity reduction; the login portal is the published route.
  • Meter removal is the supplier's job and needs a separate appointment (10 working days notice for one MPAN, 25 for several).
  • A Letter of Authority is required for 5+ connections, disconnections and, from 1 June 2026, demand of 5MVA or more; no template is published.
  • The April 2026 performance-standards summary restates SI 2015/698 with the 2026 payment table; listed once in STATUTORY_STANDARDS.
  • The unmetered portal link (a_id/1000380) was not fetched; the MPAS lookup line belongs to Meter Point Administration and is not a connections contact.

Last verified 2026-08-30.

Electricity: independent distribution network operators

Site by site, not a geographic licence area. A site on one of these applies to it, not to the regional operator; the MPAN distributor id names it where the site already has a meter.

GTC (Independent Power Networks and The Electricity Network Company)

  • 24 MPAN distributor id (Independent Power Networks Ltd (04935008) and The Electricity Network Company Ltd (05581824), trading as GTC, part of BUUK Infrastructure)
  • 27 MPAN distributor id (Independent Power Networks Ltd (04935008) and The Electricity Network Company Ltd (05581824), trading as GTC, part of BUUK Infrastructure)

Connections page: GTC (Independent Power Networks and The Electricity Network Company)

Job typesRouteHowGoes to
New connectionGTC New Connections Portal (1 to 4 residential or commercial properties)Online portalidno
New connectionApplication for a new point of connectionOnline portalidno
Capacity upgrade, Capacity reductionApplication for a change in commercial loadOnline portalidno
Divert network assets on the landApplication to divert electrical assetsOnline portalidno
  • Commercial electricity connections and load changes: 01359 302518
  • 1 to 4 property connections: 01359 243360
  • Commercial load and point of connection: POCApplications@gtc-uk.co.uk
  • Small connections: myconnections@gtc-uk.co.uk
  • 4 or more properties: sales@gtc-uk.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Distributor id 24 is Independent Power Networks Ltd and 27 is The Electricity Network Company Ltd; both point at the same GTC routes. Ids rest on a single-source cross-check, not Elexon MDD.
  • No electricity disconnection route is published (the 'redundant services' form is gas only); no temporary builder's supply route.
  • No fee amounts are published; the change-in-load and POC forms describe a free budget estimate and fee-bearing feasibility studies and formal quotations.
  • GTC also holds an ICP business; the IDNO and ICP roles can be ambiguous on a site.

Last verified 2026-08-30.

ESP Electricity

  • 25 MPAN distributor id (ESP Electricity Ltd (04718806), ESP Utilities Group)

Connections page: ESP Electricity

Job typesRouteHowGoes to
New connectionMinor works email requestEmailidno
Capacity upgrade, Move the supply positionMoving or upgrading your connectionEmailidno
  • Customer services: 01372 587 500
  • Connections and alterations: ESPEminorworks@espug.com
  • General: hello@espug.com
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No published route for disconnection or temporary builder's supply; use the minor works email.
  • No connection fees or timescales are published.

Last verified 2026-08-30.

Last Mile Electricity

  • 26 MPAN distributor id (Last Mile Electricity Ltd (SC234694, formerly Energetics Electricity), Last Mile Asset Management)

Connections page: Last Mile Electricity

Job typesRouteHowGoes to
New connectionPoint of connection requestEmailidno
Capacity upgradeElectricity enquiriesEmailidno
  • Customer services: 03300 587 440
  • Connections and point of connection requests: CSEP-POCRequests@lastmile-uk.com
  • Electricity enquiries: Electricityinfo@lastmile-uk.com
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Last Mile's own page confirms id 26 ('if those digits are 26').
  • No published routes for disconnection, diversion or temporary supply; disconnections are individually quoted.
  • Last Mile's own distributor-id table is stale for other operators (it still lists Peel and G2 Energy).

Last verified 2026-08-30.

Harlaxton Energy Networks

  • 29 MPAN distributor id (Harlaxton Energy Networks Ltd (07330883), Grantham)

Connections page: Harlaxton Energy Networks (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionContact form on the single-page site (opens operator site, unverified)Phoneidno
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • HTTPS fails on both hosts (certificate name mismatch); only plain http returns 200, so nothing here is treated as observed.
  • Charging schedules are XLSX files per GSP on a legacy WordPress page.

Last verified 2026-08-30.

Leep Electricity Networks

  • 30 MPAN distributor id (Leep Electricity Networks Limited (06684589), Leep Utilities (formerly Peel))

Connections page: Leep Electricity Networks

Job typesRouteHowGoes to
New connectionCommercial project enquiry formOnline portalidno
Capacity upgradeExisting customer servicesPhoneidno
  • Customer services: 0300 373 3540
  • Existing customers: hello@leeputilities.co.uk
  • Developers and new business: salesenquiries@leeputilities.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No job-specific forms for disconnection, diversion or temporary supply.
  • The '10 working days' figure on the contact page applies to domestic enquiries only and is not published as a business timescale.

Last verified 2026-08-30.

UK Power Distribution

  • 31 MPAN distributor id (UK Power Distribution Ltd (06339585), Daresbury, Warrington)

Connections page: UK Power Distribution

Job typesRouteHowGoes to
New connection, Capacity upgrade, Permanent disconnection, Move the supply position, Divert network assets on the landApplication for services (connection, disconnection, diversion, alteration), Word template v8PDF formidno
Post-acceptance scheduling contact:
7 to 15 working days (published)
  • General: 03303 209 899
  • New connections, point of connection requests, service alterations: Newconnections@ukpowerdistribution.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Connection Offer Expenses apply at the host DNO's rates; no figures published.
  • No separate capacity reduction, meter removal or temporary supply form; the same template and email apply.
  • Publishes its own quotation timescales that mirror the statutory periods (5 working days single LV service, 15 up to 4 LV, 35 HV, 65 EHV).

Last verified 2026-08-30.

Energy Assets Networks

  • 32 MPAN distributor id (Energy Assets Networks Ltd (10068882), Energy Assets Group)

Connections page: Energy Assets Networks

Job typesRouteHowGoes to
New connectionSend an enquiry (subject Gas or Electric)Portal or formidno
  • Electricity division: 0333 666 2008
  • General: 01506 405 405
  • General: info@energyassetsnetworks.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Id 32 is reported for a different holder in one older table; treat the id as single-source.
  • No routes for capacity change, disconnection, diversion or temporary supply; no charging statement located.

Last verified 2026-08-30.

Eclipse Power Networks

  • 33 MPAN distributor id (Eclipse Power Networks Ltd (09633506))

Connections page: Eclipse Power Networks

Job typesRouteHowGoes to
New connectionContact form with 'Get Connected' and 'Asset Value Request' categoriesOnline portalidno
Capacity upgrade, Permanent disconnectionExisting connections mailboxEmailidno
  • General: 01234 486487
  • Existing connections: idno.operations@eclipsepower.co.uk
  • General enquiries: enquiries@eclipsepower.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No routes published for capacity reduction, diversion or temporary supply.
  • No Eclipse Power Networks charging statement was located; the regulated documents page lists Eclipse Power Distribution items only.

Last verified 2026-08-30.

MUA Electricity

  • 34 MPAN distributor id (MUA Electricity Ltd (10622250), mua Group)

Connections page: MUA Electricity

Job typesRouteHowGoes to
New connectionPoint of Connection application (Word)Portal or formidno
Capacity upgradeUpgrading supply (contact form)Portal or formidno
Capacity reductionReducing capacityEmailidno
Permanent disconnectionDisconnecting supplyPortal or formidno
Temporary disconnectionTemporary isolationEmailidno
Divert network assets on the landDiverting supply (contact form)Online portalidno
  • General and power cuts: 0800 011 4193
  • Capacity reductions and new connections: newconnection@muagroup.co.uk
  • Temporary isolation: operations@muagroup.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No timescales published for any job type.
  • A postcode checker at https://www.muagroup.co.uk/network-operator-lookup/ identifies mua networks because they are site specific.

Last verified 2026-08-30.

Fulcrum Electricity Assets

  • 35 MPAN distributor id (Fulcrum Electricity Assets Limited (08019627), Sheffield)

Connections page: Fulcrum Electricity Assets

Job typesRouteHowGoes to
New connectionRequest a new connectionEmailidno
Move the supply position, Capacity upgradeRequest a service alterationEmailidno
  • Customer service: 03330 146 466
  • Connection requests and service alterations: connectionrequests@fulcrum.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Fulcrum is also an ICP; /services/electricity-connections/ is the contestable-works business, not the IDNO.
  • No disconnection, capacity reduction or temporary supply routes published.

Last verified 2026-08-30.

Eclipse Power Distribution

  • 36 MPAN distributor id (Eclipse Power Distribution Ltd (02731769), the renamed former Vattenfall IDNO)

Connections page: Eclipse Power Distribution

Job typesRouteHowGoes to
New connectionContact form with 'Get Connected' and 'Asset Value Request' categoriesOnline portalidno
Capacity upgrade, Permanent disconnectionExisting connections mailboxEmailidno
  • General: 01234 486487
  • Existing connections: idno.operations@eclipsepower.co.uk
  • General enquiries: enquiries@eclipsepower.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Id 36 appears in older tables under the former Vattenfall name; the former idno.vattenfall.co.uk domain no longer resolves. Routes are shared with Eclipse Power Networks.
  • No routes published for capacity reduction, diversion or temporary supply.

Last verified 2026-08-30.

Indigo Power

  • 38 MPAN distributor id (Indigo Power Limited (12159646), Indigo Networks, Reading)

Connections page: Indigo Power

Job typesRouteHowGoes to
New connectionNew Connections (three or more connections)Emailidno
Permanent disconnectionDisconnection RequestsEmailidno
Capacity upgradeSupply Point and Existing ConnectionsEmailidno
  • Network enquiries: 0118 436 2510
  • New connections (decoded from the page): connections@indigonetworks.co.uk
  • Supply point and existing connections: spa@indigonetworks.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • The network-enquiries page mixes current indigonetworks.co.uk mailboxes with legacy sse.com ones; confirm by phone.
  • The 'metering services' block is a supplier or meter-operator matter (and likely gas) and is not an electricity route.
  • A DRAFT 2026-27 charging statement on the regulatory files page is not final.

Last verified 2026-08-30.

Stark Infra-Electricity

  • 39 MPAN distributor id (Stark Infra-Electricity Ltd (11437601), Stark Software International)

Connections page: Stark Infra-Electricity

Job typesRouteHowGoes to
New connectionStark Infra quote request formOnline portalidno
Capacity upgradeIDNO queries (MPAN, MIC)Emailidno
  • All other queries: 0333 003 0845
  • IDNO and IGT queries: networks@stark.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No customer-facing routes for disconnection, diversion or temporary supply.

Last verified 2026-08-30.

Utility Assets

  • 40 MPAN distributor id (Utility Assets Limited (07255054), London)

Connections page: Utility Assets

Job typesRouteHowGoes to
New connectionConnection enquiriesEmailidno
  • General and connection enquiries: enquiries@utilityassets.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No office phone number is published.
  • Never merge with Energy Assets Networks (id 32); they are different companies.

Last verified 2026-08-30.

Advanced Electricity Networks

  • 42 MPAN distributor id (Advanced Electricity Networks Ltd (14657793))

Connections page: Advanced Electricity Networks

Job typesRouteHowGoes to
New connectionRequest a quote (connection offer or asset value)Online portalidno
  • Enquiries: 01376 312 515
  • Enquiries: enquiries@advancedelectricitynetworks.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No routes published for existing-customer upgrades, disconnections, diversions or temporary supply.

Last verified 2026-08-30.

Independent Distribution Connection Specialists

  • 43 MPAN distributor id (Independent Distribution Connection Specialists Ltd (13901266), trading as IDCSL, H&MV Engineering Group)

Connections page: Independent Distribution Connection Specialists

Job typesRouteHowGoes to
New connectionAsset Value ApplicationPortal or formidno
  • General: 01622 933 399
  • General: info@idcsl.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No customer routes for capacity change, disconnection, diversion or temporary supply; the connection charging methodology is marked 'coming soon'.

Last verified 2026-08-30.

Aurora Utilities

  • 45 MPAN distributor id (Aurora Utilities Limited (14668032), licence granted 22 April 2024)

Connections page: Aurora Utilities

Job typesRouteHowGoes to
New connectionAsset value request formOnline portalidno
Asset value quote:
within 2 working days (published)
  • General: +44 20 3023 0200
  • General: info@aurora-utilities.co.uk
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No customer routes for capacity change, disconnection, diversion or temporary supply.

Last verified 2026-08-30.

Vital Energi Power Networks

  • 47 MPAN distributor id (Vital Energi Power Networks Ltd (15302039))

Connections page: Vital Energi Power Networks

Job typesRouteHowGoes to
New connectionProject enquiry formOnline portalidno
  • Power cut line (per FAQ): 0800 059 0129
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No IDNO email is published; no routes for capacity change, disconnection, diversion or temporary supply.

Last verified 2026-08-30.

Optimal Power Networks

Connections page: Optimal Power Networks

Job typesRouteHowGoes to
New connectionConnections mailboxEmailidno
Capacity upgradeGeneral enquiries or connections mailboxEmailidno
  • Customer and developer line: 0345 078 3237
  • Connections: OPNConnections@sse.com
  • General enquiries: opngeneralenquiries@sse.com
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • No distributor id is published for the current name; the id in older tables belongs to the former Forbury Assets name and is not carried here. Route on the operator name.
  • No disconnection, diversion or temporary supply routes published.

Last verified 2026-08-30.

Aidien

  • 46 MPAN distributor id (Aidien Limited (14616578), licence granted 12 October 2023)

Connections page: Aidien

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Licensed IDNO with no published connections route: only the Ofgem grant notice was found. Distributor id 46 rests on a single secondary source.

Last verified 2026-08-30.

E.ON UK Network Assets

  • 48 MPAN distributor id (E.ON UK Network Assets Ltd (03810087))

Connections page: E.ON UK Network Assets

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Licensed IDNO with no published connections route: only the Ofgem list entry was found. Distributor id 48 rests on a single secondary source.

Last verified 2026-08-30.

AGR Networks

  • 51 MPAN distributor id (AGR Networks Ltd (15784562))

Connections page: AGR Networks

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Licensed IDNO with no published connections route: only the Ofgem list entry was found. Distributor id 51 rests on a single secondary source.

Last verified 2026-08-30.

Sphere Energy Connect

Connections page: Sphere Energy Connect (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionUnknown (site blocked) (opens operator site, unverified)Online portalidno
  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Everything except the Ofgem licence listing is unverified; the site refuses non-browser clients.

Last verified 2026-08-30.

Green Generation Energy Networks Cymru

Connections page: Green Generation Energy Networks Cymru (opens operator site, unverified)

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Site unreachable (expired TLS certificate). Snippets describe a Welsh generation-connection grid business rather than a customer-facing embedded network; not relevant to a business connection until verified.

Last verified 2026-08-30.

Edge Utility Networks

Connections page: Edge Utility Networks

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Licensed IDNO with no website, contact, distributor id or route found.

Last verified 2026-08-30.

Grid Line Power Networks

Connections page: Grid Line Power Networks

No published application route was verified for this operator. A consultant confirms it directly.

  • An IDNO network cannot be detected from a postcode: route on the MPAN distributor id or the operator name the lookup returns.
  • Licensed IDNO with no website, contact, distributor id or route found.

Last verified 2026-08-30.

Electricity: transmission connections

Connections at transmission voltage go through the system operator with the host transmission owner. No application form: a hand-off to Purely's procurement team.

National Energy System Operator (NESO)

  • Great Britain: the single point of application for every transmission connection, progressed with the host transmission owner (NGET in England and Wales, SPT in central and southern Scotland, SHET in northern Scotland); offshore is out of scope here (National Energy System Operator (company no. 11014226 per CUSC Section 11), holder of the ESO and GSP licences)

Connections page: National Energy System Operator (NESO)

Transmission and system operator: no application form. Connections at this level go through the transmission connection process, routed to Purely's procurement team.

Non-gated connection offer after clock start (legacy CUSC clause):
three months; printed but dormant because almost all offers now follow the Gated Timetable in CUSC Section 17 (published)
Accept a Gate 2 offer / a Gate 1 offer:
90 days (Gate 2); 28 days (Gate 1) (published)
Next application window for new connection applications:
second half of 2026; no opening date published as at 30 August 2026 (observed)
Grid Code compliance process before energisation:
typically starts 12 months before commissioning (published)
  • NESO customer support; no dedicated connections line is published: 0800 464 3621, Mon to Fri 9am to 4pm
  • General customer support: box.customerservice@neso.energy
  • Connection charging queries only: transmissionconnectioncharging@neso.energy
  • Transmission connections are a hand-off: the wizard shows an explanation card and routes to the procurement team, never a form.
  • The wizard needs an MVA or export-MW input to trigger this hand-off; demand customers at distribution voltage whose load affects the transmission system go through their DNO's Statement of Works, not to NESO.
  • Meter relocation and meter removal have no NESO route: transmission metering sits under the BSC and the bilateral agreement. There is no temporary builder's supply at transmission level.
  • The legacy application forms workbook still carries a 2022 Warwick address, phone numbers and a nationalgrideso.com mailbox; none are published here.
  • The 'meter relocation or diversion' entry in the research (Exhibit I 'Change of Connection Site') is an interpretation, not a NESO service, and is not carried as a route.
  • Ofgem approved the connections reform package on 15 April 2025 (CMP434 and CMP435 implemented 10 June 2025); Gate 2 Phase 1 offers run mid-May to mid-September 2026 and Phase 2 early September 2026 to mid-January 2027. Re-check the window status weekly.
  • The role value SystemOperator is used because NESO owns no transmission assets.

Last verified 2026-08-30.

National Grid Electricity Transmission (NGET)

  • England and Wales onshore transmission at 275kV and 400kV (132kV is distribution in England and Wales under Electricity Act 1989 s.64); DNO ids 10 to 16 and 19 to 23 (National Grid Electricity Transmission plc (name as used in Ofgem licence documents; registration not verified))

Connections page: National Grid Electricity Transmission (NGET) (opens operator site, unverified)

Transmission and system operator: no application form. Connections at this level go through the transmission connection process, routed to Purely's procurement team.

  • Transmission connections are a hand-off: the wizard shows an explanation card and routes to the procurement team, never a form.
  • Every nationalgrid.com URL returned 403 to non-browser clients; all NGET URLs are search-index only and no NGET phone or email is published here.
  • No BEGA route of NGET's own was found; embedded generation agreements are applied for at NESO.

Last verified 2026-08-30.

SP Transmission (SPT)

  • Central and southern Scotland onshore transmission at 132kV and above; DNO id 18 (SP Transmission plc (per search snippet; the CUSC names both plc and Limited, not verified at Companies House))

Connections page: SP Transmission (SPT) (opens operator site, unverified)

Transmission and system operator: no application form. Connections at this level go through the transmission connection process, routed to Purely's procurement team.

  • Transmission connections are a hand-off: the wizard shows an explanation card and routes to the procurement team, never a form.
  • spenergynetworks.co.uk returned 403 to everything including robots.txt; the landing page and the Getting Connected guide are search-index URLs. No SPT phone or email is published.

Last verified 2026-08-30.

SSEN Transmission (SHET)

  • North of Scotland onshore transmission at 132kV and above; DNO id 17 (Scottish Hydro Electric Transmission plc, trading as SSEN Transmission (registered number not verified))

Connections page: SSEN Transmission (SHET)

Transmission and system operator: no application form. Connections at this level go through the transmission connection process, routed to Purely's procurement team.

Acknowledgement of an enquiry to SSEN Transmission:
within 2 business days (published)
Next new-connection application window (as stated by SSEN Transmission):
expected to open in 2026, exact date not announced (observed)
  • Existing transmission connection enquiries only, not new applications: transmission.commercial@sse.com
  • Development near transmission infrastructure: transmission.ple@sse.com
  • Transmission connections are a hand-off: the wizard shows an explanation card and routes to the procurement team, never a form.
  • Postal: SSEN Transmission, Inveralmond House, 200 Dunkeld Road, Perth PH1 3AQ. No connections phone number is published.
  • Sub-pages for preparing an application and connections reform now redirect to the landing page; only the landing and contact pages are citable.

Last verified 2026-08-30.

Gas: the 13 local distribution zones

Grouped by the four gas distribution networks. A site on an independent gas transporter applies to that transporter, which the meter lookup names.

Cadent Gas

  • EA East Anglia (Cadent Gas Limited (East of England))
  • EM East Midlands (Cadent Gas Limited (East of England))
  • NT North Thames (Cadent Gas Limited (North London))
  • NW North West (Cadent Gas Limited (North West))
  • WM West Midlands (Cadent Gas Limited (West Midlands))

Connections page: Cadent Gas

Job typesRouteHowGoes to
New connectionCadent Connections online application (household and commercial) (opens operator site, unverified)LoginOnline portalgdn
New connection, Capacity upgradeNon-Standard Connections Quotation Request Form (Version 3.0, 2025)PDF formgdn
Capacity upgradeCommercial alterations (service pipe upgrade for increased demand)Portal or formgdn
Permanent disconnectionGas disconnection application (opens operator site, unverified)LoginOnline portalgdn
Permanent disconnectionCommercial disconnectionsPortal or formgdn
Move the supply positionGas alteration application (meter or service pipe move) (opens operator site, unverified)LoginOnline portalgdn
Divert network assets on the landRequest a gas diversion (mains diversion web form)Online portalgdn
Quote validity: time to return signed acceptance and payment:
up to 90 days (published)
Average time from payment to works (new connections, disconnections, alterations):
6 to 8 weeks (published)
GT1 survey response (capacity and pressure check on an existing service):
approximately 3 weeks (published)
  • Connections team: 0800 074 5788, Mon to Fri 8am to 5pm except public holidays
  • Connections applications and enquiries (printed in the charging statement and manual form): connectionshelp@cadentgas.com
  • Plant protection (works near Cadent pipes): plantprotection@cadentgas.com
  • Portal pages returned 200 on a status check only, against a blanket robots disallow: treat portal content as unverified and the portal as login-only.
  • Meter removal is the supplier's job: both disconnection pages say the supplier must remove the meter before Cadent disconnects the service pipe.
  • Capacity reduction is not a published service; a Supply Offtake Quantity change goes through the shipper or supplier, and Cadent routes any query to 0800 074 5788.
  • No temporary builder's gas supply is published.
  • The moving-your-gas-meter page states 8am to 6pm; every other connections page says 8am to 5pm.
  • A superseded v2.0 2024 manual form (551 pounds quotation charge) is still live; do not link it.
  • Two content-asset URLs serve the same April 2026 charging statement; the information hub also links documents on a QA host that must not be used.
  • The GT1 pre-application survey (about 3 weeks) is a Cadent-specific step before an alteration for increased load.

Last verified 2026-08-30.

Northern Gas Networks

  • NO Northern (North East England and northern Cumbria) (Northern Gas Networks Limited)
  • NE North East (Yorkshire and Humberside) (Northern Gas Networks Limited)

Connections page: Northern Gas Networks (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionGet connected: apply now (online form, PDF forms or phone) (opens operator site, unverified)Portal or formgdn
New connectionBusiness and Multiple Property Application Form (opens operator site, unverified)PDF formgdn
Capacity upgrade, Move the supply positionMake changes: apply now (load increase, meter or service pipe move) (opens operator site, unverified)Portal or formgdn
Permanent disconnectionDisconnect: apply now (opens operator site, unverified)Portal or formgdn
Divert network assets on the landDiversions: moving the position of our gas main (opens operator site, unverified)Portal or formgdn
  • Every NGN URL, phone number, form name and timescale came from search snippets: nothing was read. A person must open the pages in a browser before any of it is shown as live.
  • No connections email is published here: the address seen in snippets is pattern-completed and the general customercare@ mailbox is not a connections route.
  • Multiple generations of the same form remain indexed (2017 to 2026); search engines may rank a superseded form above the current one.
  • Meter removal is a supplier task; no capacity reduction or temporary builder's supply route was surfaced (the pass-one 'temporary supply' entry was a demolition-time alteration, not a builder's supply).
  • The 21 and 20 working-day figures in snippets are not published here; they may simply restate the statutory GS6 standard.
  • A Connections Charging Methodology on the biomethane subdomain (2022) is superseded.

Last verified 2026-08-30.

SGN

  • SC Scotland (Scotland Gas Networks plc)
  • SO Southern (Southern Gas Networks plc)
  • SE South East (Southern Gas Networks plc)

Connections page: SGN

Job typesRouteHowGoes to
New connection, Capacity upgrade, Move the supply positionNon-Domestic Application Form 2025 (commercial, multiple, capacity)PDF formgdn
New connection, Capacity upgrade, Move the supply position, Permanent disconnectionYour business connection (business services landing)Portal or formgdn
New connectionApply for a new gas connection (household, single domestic property)LoginOnline portalgdn
Permanent disconnectionCommercial / Multiple Disconnection Form (03/25)PDF formgdn
Move the supply positionApply to alter your gas connection (household)LoginOnline portalgdn
Divert network assets on the landMains Diversion Application Form (02/22)PDF formgdn
Business connection, after payment received:
SGN aims to contact within 7 working days to arrange a start date (published)
Mains diversion request response:
aim to respond within 21 days (published)
Household lead time from quote acceptance to work, Scotland and Southern inside the M25:
normally 6 to 12 weeks (published)
Household lead time from quote acceptance to work, Southern outside the M25:
normally 10 to 12 weeks (published)
  • Customer service: 0800 912 1700, Mon to Fri 8.30am to 5pm
  • Mains diversions, South of England: diversionssouth@sgn.co.uk
  • The commercial return email is chosen by the geography of the work site (England or Scotland), not by job type.
  • The inside/outside M25 split is a pricing band of Southern Gas Networks plc, not a licence area, and cannot be derived from a postcode alone.
  • Meter removal is the supplier's job; capacity reduction, temporary builder's supply and meter removal are not offered as distinct services (route by phone to 0800 912 1700).
  • The Southern 4B statement URL ends in a space before .pdf; keep it encoded as %20.
  • Superseded documents remain live: Business Rules April 2025 v5, Services Charges April 2023, Notice of Rights 2024/25. Current: Business Rules April 2026 v7, Services Charges February 2026, Notice of Rights 2025/26.
  • The two passes disagree on whether the Non-Domestic form carries AcroForm fields; fillability is recorded as unknown.
  • The contact-us page returned HTTP 500 on the day; emails come from the forms and the diversion and third-party pages.

Last verified 2026-08-30.

Wales & West Utilities

  • SW South West (Wales & West Utilities Limited)
  • WN Wales North (Wales & West Utilities Limited)
  • WS Wales South (Wales & West Utilities Limited)

Connections page: Wales & West Utilities

Job typesRouteHowGoes to
New connectionOnline Quotation Portal (OQA)LoginOnline portalgdn
New connectionNew Supply Application (postcode check first)Online portalgdn
New connectionNew supply to a single domestic or commercial property, application formPDF formgdn
Capacity upgrade, Move the supply positionAlteration Application (postcode check first)Portal or formgdn
Move the supply positionMake Changes (meter move or pipe alteration)Portal or formgdn
Divert network assets on the landMain diversions (bespoke)Phonegdn
Permanent disconnectionDisconnect a gas supply (online form)Online portalgdn
Standard new connection, payment to completion:
aim within 6 weeks, up to 12 weeks depending on workload, up to 90 days if a road closure is needed (the connect page says typically 6 to 8 weeks) (published)
Contact to arrange the work after payment:
within 12 working days (published)
Meter move or service alteration, payment to completion:
typically 6 to 8 weeks (published)
  • Connections team: 0800 072 6814, Mon to Fri 8am to 8pm, Sat 9am to 2pm
  • Connections (Connections FAQ page): connections@wwutilities.co.uk
  • General enquiries: 0800 912 2999
  • Third-party UIP and IGT connections: gtuip@wwutilities.co.uk
  • Every connections page carries a template bug: the label 'For Gas Emergencies call' sits above the connections number; the genuine emergency line is separate. The 0330 number shown on the disconnect page has no verified purpose and is not published here.
  • Meter removal is arranged with the energy supplier, not WWU; WWU makes no charge for the meter-removal phase.
  • No temporary builder's gas supply is published anywhere; the charging statement covers 'temporary disconnections' (section 6.3.9) and alteration to a temporary position only.
  • Capacity reduction is not a consumer-facing product; the business rules define 'Capacity Increase / Decrease' as an alteration, and a Supply Offtake Quantity change is a shipper matter.
  • The 3,912 pounds figure is the standard domestic charge and only applies where the domestic eligibility criteria are met; a small business connection is quoted.
  • Older documents remain live and mislead: April 2020 standard charges, the 2016 methodology and the May 2024 4B statement are superseded; a 2016 leaflet points at a dead onlinequote short URL.
  • Connections terms are inside the quotation pack rather than a standalone document, so no termsUrl is recorded.
  • Gas guaranteed standards GS4 to GS10 appear in the Notice of Rights and Business Rules; they are the statutory regime listed once in STATUTORY_STANDARDS.

Last verified 2026-08-30.

Gas: independent gas transporters

One route for every independent transporter: identify the transporter for the address first, then apply to it directly.

Independent Gas Transporters

Connections page: Independent Gas Transporters

Job typesRouteHowGoes to
New connection, Capacity upgrade, Move the supply position, Permanent disconnection, Divert network assets on the landFind My Supplier (Xoserve): identify the transporter for an addressOnline portaligt
  • A postcode lookup always returns the host GDN and silently misroutes an iGT-connected site: on an existing meter route on the transporter name the CRM returns; on a new development ask whether a developer-appointed transporter was used.
  • The widely repeated '74, 75, 76 or 77' MPRN rule is wrong by omission: the IGT UNC range table v3.21 (November 2025) allocates 74,000,001 to 79,500,000 on the 8-digit core including a 78 band, and three 76/77 numbers belong to a large gas transporter. Treat any prefix test as a hint only.
  • Real MPRNs are 10 digits; the ranges are 8-digit cores with two check digits appended, so a range test must use the first 8 digits.
  • Ofgem states its licensee list is not a Formal Public Register; the count and names are as at 10 August 2026. Historic owner names in the range table (Squire Energy, Murphy Gas Networks, Energetics Gas and others) are not current transporters.
  • No per-iGT connections landing pages, contact details, fees or timescales are recorded because no individual iGT site was fetched.
  • The GDN third-party (IGT/UIP) forms at WWU and SGN are for the iGT or its contractor connecting the site network to the GDN, not for end customers.

Last verified 2026-08-30.

Water wholesalers

Anglian Water

  • East of England (Cambridgeshire, Lincolnshire, Norfolk, Northamptonshire and parts of Essex and Suffolk), water and sewerage; Hartlepool Water is an Anglian brand with a separate tariff area (Anglian Water Services Limited)

Connections page: Anglian Water

Job typesRouteHowGoes to
New connection, Capacity upgradeDevelopment Services Customer Portal: new water connection (s.45)LoginOnline portalwholesaler
Temporary builder's supplyTemporary Building Supply (TBS) via the Customer PortalLoginOnline portalwholesaler
Divert network assets on the landDiverting a public sewer; water main diversion via the Customer PortalLoginPortal or formwholesaler
Water connection: survey, cost estimate and work timeline after a paid application:
within 28 days (published)
Local authority road permit where required:
minimum three months to apply for (published)
Re-estimate or re-survey on request:
within 28 calendar days (published)
  • Development Services (option 1 water connections, option 2 drainage, option 5 portal help): 03456 066 087, Mon to Fri 8am to 5pm
  • Water connections: connections@anglianwater.co.uk
  • Sewer connections and diversions: drainage@anglianwater.co.uk
  • Non-household disconnections are requested from the retailer, not Anglian (the disconnection FAQ says so); the household route is an email to a disconnections mailbox.
  • The portal is mid-migration from InFlow to the new Development Services portal; which login applies depends on application type.
  • Anglian's robots.txt disallows /SysSiteAssets/ and the self-lay notification forms, so the charging arrangements and paper forms under those paths were not read.
  • No capacity reduction or meter relocation route is published.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Northumbrian Water

  • North East England (water and sewerage), trading as Northumbrian Water (Northumbrian Water Limited, trading as Northumbrian Water in the North East and Essex & Suffolk Water in the South East)
  • Essex and Suffolk (water supply only; sewerage is another undertaker, typically Anglian Water or Thames Water), trading as Essex & Suffolk Water (Northumbrian Water Limited, trading as Northumbrian Water in the North East and Essex & Suffolk Water in the South East)

Connections page: Northumbrian Water

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyDeveloper Services portal (Salesforce): water connection applicationLoginOnline portalwholesaler
Divert network assets on the land2026 Mains Diversion Application Form (NW)PDF formwholesaler
Water connection quote after the application is accepted:
aim to provide within 28 days (published)
Water connection after the quote is paid and private pipework passes inspection:
within 21 days; up to 12 weeks where traffic management is required (published)
Online contact form response:
two working days (published)
  • Water connections: 0345 609 4639, Mon to Fri 9am to 4pm
  • Sewer connections: 0333 321 4952
  • Water connections: newdevelopmentwater@nwl.co.uk
  • Sewer connections: newdevelopmentsewerage@nwl.co.uk
  • Essex & Suffolk Water pages (eswater.co.uk) were not separately read; the charging document covers both trading areas.
  • A standalone disconnection is included in a new connection application or requested by phone; the FAQ number could not be confirmed and is not published.
  • The diversion team mobile number on the diversion page is volatile and not published here.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Severn Trent Water

  • The Midlands from the Bristol Channel to the Humber and the Welsh border to the East Midlands (water and sewerage); sewerage only inside the South Staffs Water supply area (Severn Trent Water Limited)

Connections page: Severn Trent Water

Job typesRouteHowGoes to
New connection, Capacity upgradeApplication forms and guidance: new water connection (25mm to 32mm, 50mm or more), split from a shared supplyPortal or formwholesaler
Divert network assets on the landMove our water assets (diversion); move our waste assets (diversion)Portal or formwholesaler
  • Developer services: 0800 707 6600, Mon to Thu 9am to 4pm, Fri 9am to 3.30pm
  • The developer contact page is disallowed in robots.txt and was not fetched; contacts come from the charging PDF and the contact-list PDF.
  • Disconnection: the disconnecting-and-reconnecting page describes permanent and temporary disconnection via online forms whose links are client-rendered; for a business start with the retailer.
  • No published quotation or connection timescales were found; a 'quotes valid six months' snippet was not verified.
  • st-connect.co.uk is Severn Trent Connect (a wastewater and NAV business), not the application portal. The sitemap's /building-and-developing/overview/ tree is entirely 404.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

South West Water

  • Cornwall, Devon and parts of Somerset and Dorset (water and sewerage) (South West Water Limited (includes the Bournemouth Water area of supply and the Isles of Scilly))
  • Bournemouth Water area (water only, own developer site at bournemouthwater.co.uk, not fetched) (South West Water Limited (includes the Bournemouth Water area of supply and the Isles of Scilly))
  • Isles of Scilly (water and sewerage since 2020) (South West Water Limited (includes the Bournemouth Water area of supply and the Isles of Scilly))

Connections page: South West Water

Job typesRouteHowGoes to
New connection, Capacity upgradeGetting a new water connection (in-page online form)Online portalwholesaler
Temporary builder's supplyStandpipe hire (temporary supply from hydrants)Online portalwholesaler
Divert network assets on the landWater main diversionOnline portalwholesaler
  • Developer Services help desk: 0800 083 1821, Mon to Thu 8.30am to 4.30pm, Fri 8.30am to 4pm
  • No developer services email is published; only a NAV mailbox exists. Contact is by phone and post.
  • No disconnection, capacity reduction or meter removal route is published on the verified pages.
  • Bournemouth Water and Bristol Water are brands of South West Water Limited with their own developer sites (not fetched); a BH or BS postcode needs those routes for water supply.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Southern Water

  • South East England: sewerage across Kent, Sussex, Hampshire and the Isle of Wight; water supply only in its own smaller districts (only Kent and West Sussex were evidenced in the charging scheme) (Southern Water Services Limited)

Connections page: Southern Water

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyGetConnected portal: s.45 new water connectionLoginOnline portalwholesaler
Divert network assets on the landWater main diversion (s.185)LoginOnline portalwholesaler
s.45 water connection application review:
within five days (published)
Site survey and price for the water connection:
within 28 days (published)
Water regulations consent:
within 10 days (published)
Traffic permit where required (third party):
up to 3 months (published)
  • Developer Services (option 5): 0330 303 0119, Mon to Thu 9am to 5pm, Fri 9am to 4pm
  • Developer services: developerservices@southernwater.co.uk
  • Water connection technical queries: s45techqueries@southernwater.co.uk
  • Wastewater connections: sewerconnections@southernwater.co.uk
  • This is the clearest verified capacity-upgrade route among the water companies: the same s.45 application covers upgrading or replacing an existing supply to increase flow.
  • No standalone disconnection route was verified; a disconnection can be quoted as part of a connection job. Infrastructure charges were read from a laid-out table and should be checked against it.
  • The water-supply districts are far smaller than the sewerage area; the postcode map is sewerage-led and needs district-level water and sewerage columns.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Thames Water

  • London and the Thames Valley (water and sewerage) (Thames Water Utilities Limited (from general knowledge; not confirmed on a fetched page))

Connections page: Thames Water

Job typesRouteHowGoes to
New connectionApply for a new water connection (online journey)Online portalwholesaler
New connection, Capacity upgradeNew mains and water connections application (fillable, 21 pages)PDF form, fillablewholesaler
Temporary builder's supplyApplication to use an existing water supply for building purposes (fillable)Portal or form, fillablewholesaler
Divert network assets on the landApply for a water main diversion (fillable)PDF form, fillablewholesaler
New water service connection: connection date after quote acceptance:
typically up to three months for permissions; the work itself up to four days (published)
New water main construction:
within 90 days of accepting the quote (published)
Acknowledgement of an emailed application (DS reference and amount payable):
within 2 days (published)
Permanent disconnection (developer route):
call within 7 days; mark-up visit within 14 days; disconnection within 21 days after mark-up, often longer for road permits (published)
  • Developer Services: 0800 009 3921, Mon to Fri 8am to 5pm, closed bank holidays
  • Developer Services: developer.services@thameswater.co.uk
  • The legacy host developers.thameswater.co.uk does not resolve; search engines still surface forms there. Never link it.
  • A fillable disconnection form exists (application-for-a-disconnection.pdf, free, registered owner must authorise) but non-household customers are told to contact their retailer, so it is not carried as a route.
  • Meter moves: the household route is a phone survey; non-household meter changes go through the retailer. No capacity reduction or meter removal route is published.
  • Postal address Clearwater Court, Vastern Road, Reading RG1 8DB; an online enquiry form exists at https://www.thameswater.co.uk/developers/contact/enquiry.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

United Utilities

  • North West England (Cumbria, Lancashire, Greater Manchester, Merseyside, Cheshire), water and sewerage (United Utilities Water Limited (contact page names United Utilities Group PLC, Haweswater House, Lingley Mere Business Park, Warrington WA5 3LP))

Connections page: United Utilities

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyApply for a new water connection (AWS1 online web form for houses; AWS2 flats and AWS3 commercial PDFs)Portal or form, fillablewholesaler
Divert network assets on the landWater main diversion application (March 2026)PDF formwholesaler
New water connection quote:
within 28 calendar days (published)
New water connection completion after payment and inspection:
within 21 calendar days, subject to traffic management (published)
Temporary (building) supply validity:
12 months, reviewed annually (published)
Water main diversion (large developments):
up to 6 months from initial enquiry (published)
  • Developer Services (option 2 wastewater): 0345 072 6067, Mon to Fri 8am to 6pm
  • Large developers, self-lay providers, NAVs and diversions: 0345 026 8989, Mon to Fri 8am to 5pm
  • Water: developerserviceswater@uuplc.co.uk
  • Wastewater: wastewaterdeveloperservices@uuplc.co.uk
  • Commercial disconnection is 'managed by the retailer and carried out by our network teams' (verbatim), so it is not a wholesaler route; household demolition has phone lines.
  • The household meter relocation form (126.23 pounds) is a metering route, not a developer or B2B route, and is not carried.
  • The published levels of service (SAM and SLPM codes) cover sewer adoption and self-lay, not standard connections, and are not reproduced.
  • A free water connection budget calculator exists at https://www.unitedutilities.com/builders-developers/water-services/water-connections/water-connection-calculator/
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Wessex Water

  • Dorset, Somerset, most of Wiltshire and parts of Gloucestershire and Hampshire (water and sewerage); sewerage only in Bristol and Bath, where Bristol Water supplies water (Wessex Water Services Limited (developer materials brand as YTL Wessex Water))

Connections page: Wessex Water

Job typesRouteHowGoes to
New connectionApply for a water connection online (developer portal)LoginOnline portalwholesaler
New connectionSite connections (multi-property developments, water and sewer)LoginOnline portalwholesaler
Temporary builder's supplyPortable standpipe hire (via Aquam) or building water through the supply connection (opens operator site, unverified)Portal or formwholesaler
Divert network assets on the landWater main diversion (via the developer portal dashboard)LoginOnline portalwholesaler
New water supply connection:
acknowledged within 5 calendar days; site visit and quotation within 28 days; quote valid at least one month or to the end of the financial year; price valid 3 months after payment (published)
New water main (requisition):
acknowledged within 5 working days; fixed quote within 28 calendar days (42 for sites over 500 properties) (published)
  • New water supply connections: 01225 526222, Mon to Thu 8am to 4.30pm, Fri 8am to 4pm
  • New sewerage connections, build-over and mapping: 01225 526333
  • Water connections and disconnections: water.connection@wessexwater.co.uk
  • Sewer connections: sewer.connection@wessexwater.co.uk
  • The content host developerservices.wessexwater.co.uk refuses the WebFetch client with 403 and was read with a plain desktop browser user agent; the first research pass saw 403 on every path. Re-confirm in a browser before relying on it.
  • A fillable disconnection form (WWDS-DEV-003A) exists for domestic disconnections; non-domestic customers are told to contact their retailer, so it is not carried as a route.
  • No capacity upgrade, capacity reduction or meter relocation route is published on the developer site.
  • The developers.wessexwater.co.uk portal ids are not symmetrical: /OtherSewerConnection/Index/1000 exists, /OtherWaterConnection/Index/1000 is 404.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Yorkshire Water

  • Yorkshire (water and sewerage); the 'parts of North Lincolnshire and Derbyshire' wording is unsourced (Yorkshire Water Services Ltd)

Connections page: Yorkshire Water

Job typesRouteHowGoes to
New connection, Temporary builder's supplyConnectMe (free budget estimate or full application)LoginOnline portalwholesaler
New water connection:
receipt confirmed within 5 days; quote within 28 days of a completed application; connection within 21 days of the checklist; up to three months where council notice is needed (published)
Quote validity:
6 months from issue (published)
Permanent water disconnection (developer route):
initial response within 5 days; surveyor visit within 28 days; disconnection normally within 28 days (published)
  • Developer Services (option 2 clean water, option 1 sewerage): 0345 120 84 82, Mon to Fri 8am to 5pm
  • Clean water: wbu.service.centre@yorkshirewater.co.uk
  • Sewerage: technical.sewerage@yorkshirewater.co.uk
  • No capacity upgrade, capacity reduction or meter relocation route is published; no water main diversion form was located beyond the charge line.
  • The free developer disconnection route via ConnectMe is for demolition sites; a business starts with its retailer.
  • Legacy /media7/ PDFs still resolve but are not linked from the current site.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Hafren Dyfrdwy

  • Wrexham area of north east Wales (former Dee Valley Water) (Hafren Dyfrdwy Cyfyngedig (Severn Trent group))
  • Powys and mid Wales (former Severn Trent Wales); in much of its area sewerage is provided by Dwr Cymru Welsh Water, boundary unverified (Hafren Dyfrdwy Cyfyngedig (Severn Trent group))

Connections page: Hafren Dyfrdwy

Job typesRouteHowGoes to
New connection, Temporary builder's supplyWater connections application form, Wrexham area (fillable, 10 pages)PDF form, fillablewholesaler
Divert network assets on the landDiversion of a water main application (fillable, 7 pages)PDF form, fillablewholesaler
  • Developer Services: 0330 678 1481, Mon to Thu 9am to 4pm, Fri 9am to 3.30pm
  • Most building-and-developing pages in the site's own sitemap return 404 (overview, water and sewer connection, temporary supply, diversions, commercial property, charges); only the forms page and the get-in-touch forms are live.
  • Two-area split: separate Wrexham and Powys forms; a Powys-only large diameter connections form exists but is an analogy for a bigger supply, not a published capacity upgrade route.
  • Business premises disconnections go through a retailer (stated on the permanent disconnection page); the online disconnection forms are household or developer routes.
  • /developers/ redirects to an unresolvable internal host; do not use it as a landing URL.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Dwr Cymru Welsh Water

  • Most of Wales plus Herefordshire and parts of Cheshire and Gloucestershire (water and sewerage) (Dwr Cymru Cyfyngedig (Glas Cymru group))

Connections page: Dwr Cymru Welsh Water

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyNew water connections, standard size (portal application; information page)LoginOnline portalwholesaler
New connectionLarge diameter or fire sprinkler connection over 63mm application (PDF, 8 pages)Emailwholesaler
Divert network assets on the landAlteration or removal (including diversion) of a water mainLoginOnline portalwholesaler
Standard new water connection:
application reviewed within 5 calendar days; quote within 28 days of a full application; trench inspection within 5 working days; connection within 21 days after inspection (published)
  • Developer Services: 0800 917 2652, Mon to Fri 8.30am to 5pm
  • Developer Services (printed on the large-diameter connection page): developer.services@dwrcymru.com
  • developers.dwrcymru.com refuses the WebFetch client with 403 and was read with a plain desktop browser user agent; the first research pass saw 403 on every host. Re-confirm in a browser before relying on it.
  • No disconnection, capacity reduction or meter relocation route exists anywhere in the developer sitemap; the retailer relationship is not stated on the developer pages.
  • The payment portal link on the charges page (developerservices.dwrcymru.com) returns 404; pay at https://developers.dwrcymru.com/en/my-account/pay-your-quotation.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Affinity Water

  • North and West London and the surrounding Home Counties, in Central, East and Southeast regions; water supply only (sewerage by Thames Water or Anglian Water in the Central region, Anglian Water in the East and Southern Water in the Southeast) (Affinity Water Limited (company no. 02546950))

Connections page: Affinity Water

Job typesRouteHowGoes to
New connection, Capacity upgradeMy Developments portal (Development Experience)LoginOnline portalwholesaler
Temporary builder's supplyApply for a temporary supply (My Developments portal); hydrant licence alternativeLoginOnline portalwholesaler
Divert network assets on the landWater mains diversion application (s.185, My Developments portal)LoginOnline portalwholesaler
New water main application: cost advice:
within 28 calendar days of receiving the application (published)
  • Development Experience: 0345 357 2428, Mon to Thu 8.30am to 5pm, Fri 8.30am to 4.30pm
  • Development Experience (also the charging arrangements enquiry address): dx@affinitywater.co.uk
  • affinitywater.co.uk is a single-page app that returns 200 for every path including invented ones, so an HTTP status is no evidence a page exists; the pages above were read in a rendered browser. Link checkers must not trust a 200 from this host.
  • A disconnection application exists in the portal (free), but on an existing SPID the retailer comes first.
  • No capacity reduction, meter removal or meter relocation route was found.
  • The '5 steps to connection' PDF URL returns the HTML app shell, not a PDF.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Portsmouth Water

  • South Hampshire and parts of West Sussex; water supply only (sewerage normally Southern Water); does not cover the Isle of Wight (Portsmouth Water Ltd)

Connections page: Portsmouth Water

Job typesRouteHowGoes to
New connection, Temporary builder's supplyApplication for New Water Supply (service connection form or developer portal)Portal or form, fillablewholesaler
Divert network assets on the landMains diversion application formEmailwholesaler
Service connection: survey and quote:
within 28 days of receipt of the application fee (published)
Mains requisition: acknowledgement and design:
acknowledgement within 5 days; design and terms within 28 days of a complete application (published)
Developer portal account approval:
within 5 working days (published)
  • Developer Service team (service connections): 023 9244 9088, Mon to Fri 8.30am to 4.30pm
  • New Development team: 02392 249 327
  • Developer services: developer.services@portsmouthwater.co.uk
  • No disconnection, meter removal, meter relocation, capacity upgrade or capacity reduction route is published; the pre-development enquiry and the standard application are the nearest routes.
  • The widely indexed www.portsmouthwater.co.uk/developers/new-services/ redirects to a double-slash URL and the single-slash form is 404; use the developers subdomain and its /developments/* children.
  • The rates.ts wholesaler table wrongly gives Portsmouth Water the Isle of Wight; Southern Water supplies it.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

South East Water

  • Kent, Sussex, Surrey, Hampshire and Berkshire; water supply only (wastewater by Thames Water, Southern Water, Severn Trent Connect or Icosa Water depending on location) (South East Water Limited, Developer Services, Rocfort Road, Snodland ME6 5AH)

Connections page: South East Water

Job typesRouteHowGoes to
New connection, Capacity upgradeNew service connection application (application form portal)Online portalwholesaler
Temporary builder's supplyTemporary supply application formOnline portalwholesaler
Divert network assets on the landC3 diversion (C4 diversion at /water-connections/c4-diversion/)Online portalwholesaler
New service connection quote:
within 28 days of submitting and paying for the application (published)
New service connection works:
within 21 days in most circumstances; up to 12 weeks if traffic sensitive (published)
  • Developer Services: 0333 000 0060, Mon to Fri 8am to 4pm
  • Developer Services: developer.services@southeastwater.co.uk
  • No disconnection, meter removal, meter relocation or capacity reduction route exists on the portal or in its sitemap.
  • Developer content lives on the www.developers subdomain; the main-site /developer-services/ and the indexed /developer-portal/ paths are 404. The Australian southeastwater.com.au is a different company.
  • Its NAV page is a good primary source on NAV mechanics, but its SLAs are South East Water's, not a NAV route's.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

South Staffs Water

  • Staffordshire and parts of the West Midlands from Ashbourne to Halesowen and Burton-upon-Trent to Kinver; water supply only (sewerage by Severn Trent Water) (South Staffordshire Water PLC (South Staffs region; the same licence also covers the Cambridge region))

Connections page: South Staffs Water

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyStandard 25mm connection form and non-standard 32mm or larger form (both fillable)PDF form, fillablewholesaler
Divert network assets on the landDiversion form (/media/kk1bxoly/diversion-form.pdf, fillable)PDF form, fillablewholesaler
New connection: receipt, quote, inspection, connection:
5 days; 28 days; 5 days; 21 days (about 3 months if a road closure is needed) (published)
Mains diversion: quote and works:
42 days; 90 days (published)
  • Developer Services: 0345 345 1399
  • Applications, agreements and payments: developerservices@south-staffs-water.co.uk
  • Service requests: Servicerequests@south-staffs-water.co.uk
  • Cambridge Water is the same company and licence but has its own developer contacts and form URLs; route a Cambridge-region site to the cambridge-water record.
  • No disconnection, meter removal or capacity reduction route is published.
  • A separation or replacement connection form exists for splitting a shared supply or replacing a connection up to 25mm.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Cambridge Water

  • Cambridge and the surrounding area from Ramsey in the north to Melbourn in the south and Gamlingay in the west; water supply only (sewerage by Anglian Water) (South Staffordshire Water PLC trading as Cambridge Water, 90 Fulbourn Road, Cambridge CB1 9JN)

Connections page: Cambridge Water

Job typesRouteHowGoes to
New connection, Capacity upgrade, Temporary builder's supplyStandard 25mm connection form and non-standard 32mm or larger form (both fillable)PDF form, fillablewholesaler
Divert network assets on the landDiversion form (/media/yljj5if4/diversion-form.pdf)PDF formwholesaler
New connection: receipt, quote, inspection, connection:
5 days; 28 days; 5 days; 21 days (typically three months if a road closure is needed) (published)
  • Developer Services: 01223 403115
  • Developer Services (Cambridge region): CamNetDev@south-staffs-water.co.uk
  • Cambridge Water is the Cambridge region of South Staffordshire Water PLC, not a separate appointed undertaker; it is kept as a record because contacts and form URLs differ.
  • No disconnection, meter removal or capacity reduction route is published.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

SES Water

  • Parts of Surrey, Kent and south London; water supply only (sewerage by Thames Water or Southern Water depending on location) (SES Water, London Road, Redhill RH1 1LJ)

Connections page: SES Water

Job typesRouteHowGoes to
New connectionNew connections application (online page) or DS New Connection Application Form (.docx)Portal or formwholesaler
Capacity upgradeApplication to upgrade existing supplyOnline portalwholesaler
Temporary builder's supplyStandpipe hire (temporary water from hydrants)Phonewholesaler
New connection estimate:
within 28 calendar days of confirming a complete application (published)
  • Developer Services: 01737 772000, Mon to Fri 9am to 3pm
  • Developer Services: developerservices@seswater.co.uk
  • No disconnection, meter removal, meter relocation, mains diversion or capacity reduction route was found in the developers section or the sitemap.
  • Use the www host and the /developers/services/ prefix; the apex host and the indexed shorter paths are 404.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Scottish Water

  • Scotland: water and sewerage for all Scottish postcodes; a single national provider, so no second sewerage undertaker and no NAV regime (Scottish Water, a body corporate established by section 20 of the Water Industry (Scotland) Act 2002)

Connections page: Scottish Water (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionDevelopment Services application (unverified) (opens operator site, unverified)Portal or formwholesaler
  • Nothing was verified: every URL is search-index derived and must be opened in a browser before it is shown as live. No phone or email is published here.
  • Non-household customers in Scotland are billed by a Licensed Provider (retailer) under the WICS-regulated retail market; connections are still applied for at Scottish Water, and the Licensed Provider route for disconnections is a hint from a URL path only.
  • The guessed host developerportal.scottishwater.co.uk does not resolve; do not use it.
  • On an existing non-household supply (a SPID) disconnection, temporary disconnection, meter removal and meter relocation start with the water retailer, not the wholesaler; wholesaler disconnection routes are for developer and demolition sites.
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site; confirm the undertaker from the bill or adoption paperwork.

Last verified 2026-08-30.

Other water routes

Not wholesalers. A development can be served by a new appointment (NAV) instead of the incumbent, which a postcode cannot detect, and the contestable works on a new connection can be self-laid by an accredited provider.

New Appointments and Variations (NAV) route

  • England and Wales, site by site: a NAV holds the appointment for a defined development area (unserved site, incumbent consent, or a premises using at least 50 megalitres a year in England or 250 in Wales, WIA 1991 s.7); no NAV regime exists in Scotland (Ofwat-appointed site-specific water and/or sewerage undertakers (limited companies appointed per site))

Connections page: New Appointments and Variations (NAV) route

Job typesRouteHowGoes to
New connectionIncumbent-side NAV route (South East Water example): NAV enquiry, site status letter, bulk supply offerOnline portalwholesaler
New connectionNAV-side example: Albion WaterPortal or formwholesaler
  • A postcode lookup returns the incumbent and is silently wrong on a NAV site: two addresses in one postcode district can have different undertakers. Ask the customer whether the site is a new development on an independent network and check the bill or adoption paperwork.
  • Ofwat's register of NAVs granted to date is the only authoritative list and could not be retrieved (403). CCW lists eleven NAVs (Advanced Water Infrastructure Networks / Leaf Water, Albion Water, County Water, ESP Utilities Group, Independent Water Networks, Last Mile Water, LEEP Utilities, Matrix Water, MUA Water, Severn Trent Services, Veolia Water Tidworth) but that is not the register; the Independent Networks Association member list is not a NAV list either.
  • The South East Water SLAs on its NAV page (5, 21, 28 and 90 days) are the incumbent's commitments, not a NAV route timescale.

Last verified 2026-08-30.

Self-lay under WIA 1991 s.51A (WIRS-accredited providers)

  • England and Wales (every incumbent accepts self-lay for contestable work; the final connection to the live main stays non-contestable); the register also covers Scotland and Northern Ireland (Accredited Self-Lay Providers on the Water Industry Registration Scheme register operated by LRQA)

Connections page: Self-lay under WIA 1991 s.51A (WIRS-accredited providers)

Job typesRouteHowGoes to
New connectionWIRS / WIRSAE accredited provider searchOnline portalwholesaler
  • LRQA UK: +44 121 817 4300
  • Self-lay is an alternative delivery route for contestable new mains and services, not an application route for disconnection, meter removal or capacity reduction.
  • WIRS is operated by LRQA at lrqa.com; every lr.org WIRS path is 404 and operator pages that still say 'Lloyd's Register' are stale.
  • WIRS and WIRSAE are different accreditations: WIRSAE providers are contracted by retailers for temporary or permanent disconnections and meter installation. Accreditation scope is per organisation, so check the scope, not just the listing.
  • The Water UK Codes for Adoption live on water.org.uk, which serves a Cloudflare challenge to automated clients; the South Staffs codes page is a reachable description.

Last verified 2026-08-30.

Frequently asked questions

Who receives a utility connection application?
The network operator for the utility at your postcode: the distribution network operator for electricity, the gas transporter for gas and the wholesaler for water. That covers a new connection, a capacity change, a move of the supply position, a diversion and a permanent disconnection. Jobs on the meter itself (removal, a meter-only move, de-energising and re-energising for works, and on water any job on an existing supply point) go to your supplier or water retailer, because the supplier owns the meter. The tool checks the party first, then names the form.
How do I find which operator serves my postcode?
Enter the site postcode in the tool. If the site already has a meter, pick the address and the operator is read from the meter identifier: the distributor id at the start of an electricity MPAN, the transporter recorded against a gas MPRN, or the wholesaler behind a water SPID, which is exact. On a bare site the operator comes from the postcode alone and is labelled likely, because a postcode cannot tell whether a development is served by an independent network, an independent gas transporter or a new appointment for water instead of the regional operator.
How long does the operator have to send a quotation?
Electricity: the Electricity (Standards of Performance) Regulations 2015 set 5 working days for a single low-voltage single-phase connection, 15 for a small low-voltage project, 25 for other low-voltage connections, 35 for high voltage and 65 for extra-high voltage, from a complete application. Gas: the Gas (Standards of Performance) Regulations 2005 set 4 working days for a standard quotation at or below 275 kWh per hour, 11 for a non-standard quotation at that size and 21 above it. Water: neither instrument sets a quotation period, so the wholesaler's own published levels of service apply. Which period applies is the operator's determination.
What does a connection application need?
A site location plan showing the boundary and the proposed supply position, the load (a schedule of plant in kW or kVA for electricity, the peak hourly load for gas, the flow and pipe size for water), the meter identifier and a recent bill where a supply already exists, proof of title or landowner consent on a bare site or a diversion, a letter of authority where someone applies on the business's behalf, and the programme dates. The result card in the tool lists exactly which of these your job needs.
What is the difference between a service alteration and a diversion?
A service alteration moves your own supply position: the incoming cable, pipe or cut-out goes to a new place on the premises. A diversion moves the network's own assets, such as a cable or main crossing the land, so that you can build. They are different teams and different forms at every operator, and moving only the meter with no cable or pipe change is a third case that belongs to your supplier. The tool separates the three so the application lands with the right team.
Does one application cover electricity, gas and water?
No. Each utility has its own operator, its own forms and its own rules on who receives the job, so a site that needs more than one connection makes one application per utility. Run the tool once per utility; the answers for the site are kept in this browser tab, and each utility has its own page with the routing table, statutory rows and questions for that network: electricity, gas and water.
When does the statutory clock start?
On receipt of a complete application. An application missing the site plan, the load or the authority to act is not complete, and the quotation period does not run until the operator has what it needs. That is why the tool lists the documents for the job before you apply. The operator decides which standard applies to a given job; the tool shows every quotation row for the utility and highlights the one its reading of your answers points to.
Is the application service free?
Yes. We complete the operator's application on the operator's own form and submit it with your authority at no fee. We are paid on the supply contract too, disclosed. On the ongoing gas and electricity contract we earn a commission built into the unit rate (stated in pence per kWh) or an agreed fee, your choice. Every margin is separated so you can see exactly what the service costs.
Does this tool cover Scotland, Wales and independent networks?
The fourteen electricity licence areas include Scotland and Wales, as do the thirteen gas local distribution zones, and the water wholesalers listed include Scottish Water, Dwr Cymru Welsh Water and Hafren Dyfrdwy. A site on an independent distribution network operator (an MPAN distributor id of 24 or above), an independent gas transporter or a new appointment for water applies to that operator instead, which a postcode cannot detect. Where the site already has a meter the tool reads the operator from the meter identifier; on a bare site it asks whether the development has its own network before trusting the postcode.

Sources

Statutory quotation periods from the Electricity (Standards of Performance) Regulations 2015 (SI 2015/698) and the Gas (Standards of Performance) Regulations 2005 (SI 2005/1135), read alongside Ofgem's 2026 guaranteed standards of performance guidance. Water connections are made under section 45 of the Water Industry Act 1991, which sets no quotation period. Application routes, forms, contacts and fee positions from each operator's own website, fetched and read where the operator allows it and otherwise marked unverified. Nothing on this page is estimated by Purely Energy; where a figure or a route could not be verified, the page says so.

The right form, to the right party, first time

Tell us the site and the load. We complete the operator's application on the operator's own form, submit it with your authority, tender the contestable works and place the supply contract on the new meter. No fee for the application.