Gas connection application

A gas connection application goes to the gas transporter for your postcode, or to your supplier where the job is the meter or the offtake quantity: this tool names the transporter, the form and the statutory quotation period for your job type.

Routes verified against each operator's published process, August 2026

Free interactive application finder

Five short steps. Your answers stay in this browser tab; nothing is sent until you ask us to prepare the application.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5

Step 1 of 5: Site

Where is the site?

The postcode of the site itself, not your head office. It decides which network operator you apply to.

UK business premises only. We never look up or cold-call domestic customers.

Transporter or supplier, and what the regulations say about the wait

Gas has two parties where electricity has one. The gas transporter owns the mains and the service pipe: one of the four gas distribution networks (Cadent, Northern Gas Networks, Wales & West Utilities and SGN) across thirteen local distribution zones, or an independent gas transporter where a developer had the site network built and adopted separately. Your supplier acts as the shipper on that network and owns the meter. The transporter takes a new business gas connection, an alteration for more load, a move of the service pipe, a diversion of a main and a permanent disconnection of the service; everything on the meter and everything on the agreed offtake goes through the supplier.

That split decides three jobs that look like network jobs but are not. Capping and uncapping the meter for works is done by the supplier's meter operator, not the transporter. A change to the Supply Offtake Quantity, the hourly figure the site is registered to draw, is made by the supplier as shipper, so a capacity reduction on gas never goes to the network. And a permanent disconnection runs in two halves: the supplier has the meter removed first, then the transporter disconnects the service pipe. The tool routes each of these to the supplier registered at the site.

The independent gas transporter question is the one a postcode cannot answer. A postcode lookup always returns the host distribution network and is silently wrong on a site whose network belongs to an independent transporter. Where a meter exists the tool reads the transporter recorded against the MPRN, which is exact; on a bare development it asks whether a developer-appointed transporter was used. The business gas supplier lookup answers the supplier half of that from the same postcode.

The statutory clock is the Gas (Standards of Performance) Regulations 2005: 4 working days for a standard quotation at or below 275 kWh per hour, 11 for a non-standard quotation at that size and 21 above it, from a complete application. The peak hourly load you give also sets the meter size, which is why the tool asks for it; the costs behind a gas connection are in our guide to new connection costs. Electricity and water have their own pages: the electricity connection application and the water connection application. When the gas is on, request a business gas quote and we tender the supply contract on the new meter.

Statutory quotation timescales for gas

Working days from a complete application, set by the Gas (Standards of Performance) Regulations 2005 rather than by the transporter.

ScenarioQuotation withinInstrument
Standard quotation: new connection or alteration up to and including 275 kWh/h, or a disconnection up to 2 bar, with no site visit (GS4)4 working daysSI 2005/1135
Non-standard quotation up to 275 kWh/h (GS5)11 working daysSI 2005/1135
Non-standard quotation over 275 kWh/h (also mains diversions and disconnections at 2 bar and above) (GS6)21 working daysSI 2005/1135
Response to a land enquiry (GS8):
5 working days
Commencement and substantial completion dates, connections up to 275 kWh/h (GS9):
within 17 working days of accepting the quotation
Commencement and completion dates, connections over 275 kWh/h (GS10):
within 20 working days of accepting the quotation

Working days from a complete application. Which standard applies to a job is the operator's determination; the result card highlights the row its reading of your answer points to.

Gas application routes by transporter

Every local distribution zone, grouped by gas distribution network, plus the independent gas transporter route, with the routes, contacts and timescales each publishes. 5 operators in the registry. Routes verified against each operator's published process, August 2026.

Registry verified 2026-08-30. Links appear only where the page was fetched and read; everything else is named but marked unverified until a person opens it.

Gas: the 13 local distribution zones

Grouped by the four gas distribution networks. A site on an independent gas transporter applies to that transporter, which the meter lookup names.

Cadent Gas

  • EA East Anglia (Cadent Gas Limited (East of England))
  • EM East Midlands (Cadent Gas Limited (East of England))
  • NT North Thames (Cadent Gas Limited (North London))
  • NW North West (Cadent Gas Limited (North West))
  • WM West Midlands (Cadent Gas Limited (West Midlands))

Connections page: Cadent Gas

Job typesRouteHowGoes to
New connectionCadent Connections online application (household and commercial) (opens operator site, unverified)LoginOnline portalgdn
New connection, Capacity upgradeNon-Standard Connections Quotation Request Form (Version 3.0, 2025)PDF formgdn
Capacity upgradeCommercial alterations (service pipe upgrade for increased demand)Portal or formgdn
Permanent disconnectionGas disconnection application (opens operator site, unverified)LoginOnline portalgdn
Permanent disconnectionCommercial disconnectionsPortal or formgdn
Move the supply positionGas alteration application (meter or service pipe move) (opens operator site, unverified)LoginOnline portalgdn
Divert network assets on the landRequest a gas diversion (mains diversion web form)Online portalgdn
Quote validity: time to return signed acceptance and payment:
up to 90 days (published)
Average time from payment to works (new connections, disconnections, alterations):
6 to 8 weeks (published)
GT1 survey response (capacity and pressure check on an existing service):
approximately 3 weeks (published)
  • Connections team: 0800 074 5788, Mon to Fri 8am to 5pm except public holidays
  • Connections applications and enquiries (printed in the charging statement and manual form): connectionshelp@cadentgas.com
  • Plant protection (works near Cadent pipes): plantprotection@cadentgas.com
  • Portal pages returned 200 on a status check only, against a blanket robots disallow: treat portal content as unverified and the portal as login-only.
  • Meter removal is the supplier's job: both disconnection pages say the supplier must remove the meter before Cadent disconnects the service pipe.
  • Capacity reduction is not a published service; a Supply Offtake Quantity change goes through the shipper or supplier, and Cadent routes any query to 0800 074 5788.
  • No temporary builder's gas supply is published.
  • The moving-your-gas-meter page states 8am to 6pm; every other connections page says 8am to 5pm.
  • A superseded v2.0 2024 manual form (551 pounds quotation charge) is still live; do not link it.
  • Two content-asset URLs serve the same April 2026 charging statement; the information hub also links documents on a QA host that must not be used.
  • The GT1 pre-application survey (about 3 weeks) is a Cadent-specific step before an alteration for increased load.

Last verified 2026-08-30.

Northern Gas Networks

  • NO Northern (North East England and northern Cumbria) (Northern Gas Networks Limited)
  • NE North East (Yorkshire and Humberside) (Northern Gas Networks Limited)

Connections page: Northern Gas Networks (opens operator site, unverified)

Job typesRouteHowGoes to
New connectionGet connected: apply now (online form, PDF forms or phone) (opens operator site, unverified)Portal or formgdn
New connectionBusiness and Multiple Property Application Form (opens operator site, unverified)PDF formgdn
Capacity upgrade, Move the supply positionMake changes: apply now (load increase, meter or service pipe move) (opens operator site, unverified)Portal or formgdn
Permanent disconnectionDisconnect: apply now (opens operator site, unverified)Portal or formgdn
Divert network assets on the landDiversions: moving the position of our gas main (opens operator site, unverified)Portal or formgdn
  • Every NGN URL, phone number, form name and timescale came from search snippets: nothing was read. A person must open the pages in a browser before any of it is shown as live.
  • No connections email is published here: the address seen in snippets is pattern-completed and the general customercare@ mailbox is not a connections route.
  • Multiple generations of the same form remain indexed (2017 to 2026); search engines may rank a superseded form above the current one.
  • Meter removal is a supplier task; no capacity reduction or temporary builder's supply route was surfaced (the pass-one 'temporary supply' entry was a demolition-time alteration, not a builder's supply).
  • The 21 and 20 working-day figures in snippets are not published here; they may simply restate the statutory GS6 standard.
  • A Connections Charging Methodology on the biomethane subdomain (2022) is superseded.

Last verified 2026-08-30.

SGN

  • SC Scotland (Scotland Gas Networks plc)
  • SO Southern (Southern Gas Networks plc)
  • SE South East (Southern Gas Networks plc)

Connections page: SGN

Job typesRouteHowGoes to
New connection, Capacity upgrade, Move the supply positionNon-Domestic Application Form 2025 (commercial, multiple, capacity)PDF formgdn
New connection, Capacity upgrade, Move the supply position, Permanent disconnectionYour business connection (business services landing)Portal or formgdn
New connectionApply for a new gas connection (household, single domestic property)LoginOnline portalgdn
Permanent disconnectionCommercial / Multiple Disconnection Form (03/25)PDF formgdn
Move the supply positionApply to alter your gas connection (household)LoginOnline portalgdn
Divert network assets on the landMains Diversion Application Form (02/22)PDF formgdn
Business connection, after payment received:
SGN aims to contact within 7 working days to arrange a start date (published)
Mains diversion request response:
aim to respond within 21 days (published)
Household lead time from quote acceptance to work, Scotland and Southern inside the M25:
normally 6 to 12 weeks (published)
Household lead time from quote acceptance to work, Southern outside the M25:
normally 10 to 12 weeks (published)
  • Customer service: 0800 912 1700, Mon to Fri 8.30am to 5pm
  • Mains diversions, South of England: diversionssouth@sgn.co.uk
  • The commercial return email is chosen by the geography of the work site (England or Scotland), not by job type.
  • The inside/outside M25 split is a pricing band of Southern Gas Networks plc, not a licence area, and cannot be derived from a postcode alone.
  • Meter removal is the supplier's job; capacity reduction, temporary builder's supply and meter removal are not offered as distinct services (route by phone to 0800 912 1700).
  • The Southern 4B statement URL ends in a space before .pdf; keep it encoded as %20.
  • Superseded documents remain live: Business Rules April 2025 v5, Services Charges April 2023, Notice of Rights 2024/25. Current: Business Rules April 2026 v7, Services Charges February 2026, Notice of Rights 2025/26.
  • The two passes disagree on whether the Non-Domestic form carries AcroForm fields; fillability is recorded as unknown.
  • The contact-us page returned HTTP 500 on the day; emails come from the forms and the diversion and third-party pages.

Last verified 2026-08-30.

Wales & West Utilities

  • SW South West (Wales & West Utilities Limited)
  • WN Wales North (Wales & West Utilities Limited)
  • WS Wales South (Wales & West Utilities Limited)

Connections page: Wales & West Utilities

Job typesRouteHowGoes to
New connectionOnline Quotation Portal (OQA)LoginOnline portalgdn
New connectionNew Supply Application (postcode check first)Online portalgdn
New connectionNew supply to a single domestic or commercial property, application formPDF formgdn
Capacity upgrade, Move the supply positionAlteration Application (postcode check first)Portal or formgdn
Move the supply positionMake Changes (meter move or pipe alteration)Portal or formgdn
Divert network assets on the landMain diversions (bespoke)Phonegdn
Permanent disconnectionDisconnect a gas supply (online form)Online portalgdn
Standard new connection, payment to completion:
aim within 6 weeks, up to 12 weeks depending on workload, up to 90 days if a road closure is needed (the connect page says typically 6 to 8 weeks) (published)
Contact to arrange the work after payment:
within 12 working days (published)
Meter move or service alteration, payment to completion:
typically 6 to 8 weeks (published)
  • Connections team: 0800 072 6814, Mon to Fri 8am to 8pm, Sat 9am to 2pm
  • Connections (Connections FAQ page): connections@wwutilities.co.uk
  • General enquiries: 0800 912 2999
  • Third-party UIP and IGT connections: gtuip@wwutilities.co.uk
  • Every connections page carries a template bug: the label 'For Gas Emergencies call' sits above the connections number; the genuine emergency line is separate. The 0330 number shown on the disconnect page has no verified purpose and is not published here.
  • Meter removal is arranged with the energy supplier, not WWU; WWU makes no charge for the meter-removal phase.
  • No temporary builder's gas supply is published anywhere; the charging statement covers 'temporary disconnections' (section 6.3.9) and alteration to a temporary position only.
  • Capacity reduction is not a consumer-facing product; the business rules define 'Capacity Increase / Decrease' as an alteration, and a Supply Offtake Quantity change is a shipper matter.
  • The 3,912 pounds figure is the standard domestic charge and only applies where the domestic eligibility criteria are met; a small business connection is quoted.
  • Older documents remain live and mislead: April 2020 standard charges, the 2016 methodology and the May 2024 4B statement are superseded; a 2016 leaflet points at a dead onlinequote short URL.
  • Connections terms are inside the quotation pack rather than a standalone document, so no termsUrl is recorded.
  • Gas guaranteed standards GS4 to GS10 appear in the Notice of Rights and Business Rules; they are the statutory regime listed once in STATUTORY_STANDARDS.

Last verified 2026-08-30.

Gas: independent gas transporters

One route for every independent transporter: identify the transporter for the address first, then apply to it directly.

Independent Gas Transporters

Connections page: Independent Gas Transporters

Job typesRouteHowGoes to
New connection, Capacity upgrade, Move the supply position, Permanent disconnection, Divert network assets on the landFind My Supplier (Xoserve): identify the transporter for an addressOnline portaligt
  • A postcode lookup always returns the host GDN and silently misroutes an iGT-connected site: on an existing meter route on the transporter name the CRM returns; on a new development ask whether a developer-appointed transporter was used.
  • The widely repeated '74, 75, 76 or 77' MPRN rule is wrong by omission: the IGT UNC range table v3.21 (November 2025) allocates 74,000,001 to 79,500,000 on the 8-digit core including a 78 band, and three 76/77 numbers belong to a large gas transporter. Treat any prefix test as a hint only.
  • Real MPRNs are 10 digits; the ranges are 8-digit cores with two check digits appended, so a range test must use the first 8 digits.
  • Ofgem states its licensee list is not a Formal Public Register; the count and names are as at 10 August 2026. Historic owner names in the range table (Squire Energy, Murphy Gas Networks, Energetics Gas and others) are not current transporters.
  • No per-iGT connections landing pages, contact details, fees or timescales are recorded because no individual iGT site was fetched.
  • The GDN third-party (IGT/UIP) forms at WWU and SGN are for the iGT or its contractor connecting the site network to the GDN, not for end customers.

Last verified 2026-08-30.

Frequently asked questions

Which form do I use for a gas connection application?
It depends on the gas transporter that owns the mains at your postcode, the job and, at most transporters, whether the load is standard or non-standard. Each of the four gas distribution networks publishes its own portal and forms, and each separates a household or single-property application from a business, multiple-property or non-standard form that asks for the peak hourly load, the annual load and a site plan. The tool above works out the transporter from your postcode or MPRN and names the route for your job; the routing table beneath it lists every network's published routes with the date they were verified.
Gas transporter or gas shipper: who receives the application?
The gas transporter (the distribution network, or an independent gas transporter) owns the mains and the service pipe, so a new connection, an alteration for increased load, a move of the service pipe, a diversion and a permanent disconnection go to the transporter. Your supplier acts as the shipper on that network and owns the meter, so meter removal, a meter-only move, capping and uncapping for works and any change to the Supply Offtake Quantity go to the supplier. The tool reads the supplier registered at the site so those requests start with the right party.
What if the site is on an independent gas transporter?
Apply to that transporter, not to the host distribution network. Independent gas transporters own the site network on many developments, and a postcode lookup returns the host network and is silently wrong on such a site. Where a meter exists the tool reads the transporter recorded against the MPRN, which is exact. The often-quoted rule that an independent transporter's MPRN starts 74 to 77 is incomplete: the range table allocates 74,000,001 to 79,500,000 on the 8-digit core, so treat any prefix test as a hint and trust the transporter name. On a bare development the tool asks whether a developer-appointed transporter was used.
How long does the transporter have to send a quotation?
The Gas (Standards of Performance) Regulations 2005 set the quotation periods in working days from a complete application: 4 for a standard quotation where the load is at or below 275 kWh per hour, 11 for a non-standard quotation at that size and 21 for a non-standard quotation above it. Which class applies is the transporter's determination; the result card shows all three rows and highlights the one its reading of your peak load points to.
Is a temporary builder's supply available for gas?
No. Temporary builder's supplies are an electricity product. No gas distribution network publishes one, so site heating and welfare during construction normally run on LPG or electricity. The tool keeps the option visible for gas, greyed, with that reason, so the answer is explicit rather than hidden.
How do I change the Supply Offtake Quantity?
Through your supplier, as shipper, not through the transporter. The Supply Offtake Quantity is the hourly figure the site is registered to draw, and it is part of the supply registration, so a reduction or an increase within the capacity of the existing service is a supplier request. Only where the service pipe or the meter must be upsized to carry the new load does the transporter come in, as an alteration for increased load. The tool marks a gas capacity reduction as a supplier job for that reason.
Can the gas be capped or uncapped for works?
Yes, and it is a supplier job. Capping and uncapping a gas meter is done by your supplier's meter operator, not by the transporter, so a temporary disconnection on gas goes to the supplier. A permanent disconnection is different: the transporter removes the service pipe, but only after the supplier has had the meter taken out, so a demolition or a site clearance is two requests in sequence.
Does the meter come out before a permanent disconnection?
Yes. Every distribution network treats meter removal as the supplier's job and will not disconnect a service pipe with the meter still in place, so the order is: ask the supplier to remove the meter, then apply to the transporter for the service disconnection. The tool routes the two halves to the two parties and lists the disconnection application's usual contents, which include the pipe diameter, the meter details and the reason for the disconnection.
What does a gas connection application need?
The peak hourly load and the annual load, which set the meter size and whether the quotation is standard or non-standard; a site plan showing the boundary and the proposed meter position; the MPRN and a recent bill where a supply already exists; proof of title or landowner consent on a bare site or a diversion; a letter of authority where someone applies on the business's behalf; and the programme dates. The result card in the tool lists exactly which of these your job needs.
How big is my current gas meter?
UK gas meters carry a U-series designation in which the number is the maximum flow in cubic metres per hour: a U6 passes up to 6, and diaphragm meters run from U6 to U160. The bill does not state the size, so the tool estimates it from the annual usage the industry lookup returns: usage at or below 73,200 kWh a year sits in the standard supply band that a U6 serves, and usage above that band means the meter is larger than a U6, which the annual figure alone cannot narrow further because the size is set by the peak hourly load. The exact designation is printed on the meter face, and we confirm it there before any application is submitted.
Is the application service free?
Yes. We complete the operator's application on the operator's own form and submit it with your authority at no fee. We are paid on the supply contract too, disclosed. On the ongoing gas and electricity contract we earn a commission built into the unit rate (stated in pence per kWh) or an agreed fee, your choice. Every margin is separated so you can see exactly what the service costs.

Sources

Statutory quotation periods from the Gas (Standards of Performance) Regulations 2005 (SI 2005/1135), read alongside Ofgem's 2026 guaranteed standards of performance guidance. Application routes, forms, contacts and fee positions from each transporter's own website, fetched and read where the transporter allows it and otherwise marked unverified. Nothing on this page is estimated by Purely Energy; where a figure or a route could not be verified, the page says so.

Transporter or supplier, the right one first time

Tell us the site and the peak load. We complete the transporter's application on its own form, submit it with your authority, handle the supplier half where the job needs it and place the supply contract on the new meter. No fee for the application.