The CT meter was fitted on Saturday 26 September 2026 and the supply was energised the same day, nine days after first contact. The installation took about two hours, and the supply was in place when the project needed it.
The export side is under way too. The network operator issued an export MPAN for the site's solar on 2 October, and a one-year export agreement for that solar was signed on 12 October.
Can you reduce the kVA capacity on a new connection?
Yes, but it is not quick. Here the network operator asked for about six months of usage data after the supply was energised, and the property owner has to approve any reduction. We asked on 22 and 23 September, before the supply was live, and the network operator replied on 28 September. That puts the review around March 2027, with a target of 80 kVA, band 1, the lowest band.
Because the contract is pass-through, network charges are billed at cost, so a lower capacity band comes straight off the site's bills. That is why it pays to ask early: once a supply is live, the site is held to its connected capacity until the review, which here means about six months.
How long does a new 3-phase connection take?
This one took nine days from first contact to a live supply. Once the network operator's connection is built, getting a supplier and a meter in place usually takes around two weeks in our experience, so this was quicker than usual. The installation itself took about two hours. The rest of the time went on the contract, the metering agreement and the contractor's certificates, which is why getting everything signed the day after the first call mattered.
If you have a new supply coming up, send us the network operator's connection design before you sign it and we will tell you which capacity band it puts you in and whether it is bigger than the site needs. There is no cost and you do not need to switch supplier. Start with our guide to a new electricity connection, what new connection costs look like and whether a kVA review could help your business, or send us the details through the electricity connection application.